8833 W CASHIO ST 90035
Certificate Information: 8833 W CASHIO ST 90035
- Application / Permit
- 24014-10000-02883
- Plan Check / Job No.
- B24LA12641
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: MAJOR REMODEL AND BASEMENT ADDIITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 12/4/2024
- Issuing Office
- Current Status
- CofO Issued on 5/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2024 | DANIEL YIP |
| Corrections Issued | 7/6/2024 | DANIEL YIP |
| Quality Review Completed | 7/31/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 12/3/2024 | DANIEL YIP |
| Plan Check Approved | 12/4/2024 | DANIEL YIP |
| Issued | 12/4/2024 | APPLICANT |
| CofO in Progress | 5/12/2026 | KIRK SANDERS |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
| CofO Issued | 5/22/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 8/7/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 9/3/2024 | WALLIE JONG |
| Construction near power lines | Cleared | 9/23/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/23/2024 | RIDWAN HARDY |
| Sewer availability | Cleared | 9/23/2024 | WALLIE JONG |
| Trees in Parkway | Cleared | 10/1/2024 | DYNL MIRANDA |
| Hydrant and Access approval | Cleared | 10/17/2024 | JERRY KAO |
| GPI Written Notices | Cleared | 12/3/2024 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 12/3/2024 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/12/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 1/13/2025 | Partial Approval | MEL KHACHATOURIAN |
| METHANE-Barrier | 1/16/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 1/16/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Subgrade | 1/16/2025 | Approved | MEL KHACHATOURIAN |
| Deputy Methane Barrier | 1/23/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| METHANE-Barrier | 1/23/2025 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 1/23/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 2/6/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 2/6/2025 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 2/7/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 2/19/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Deputy Shotcrete | 2/19/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 2/19/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 2/20/2025 | Approved | MEL KHACHATOURIAN |
| METHANE-Final | 2/28/2025 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 2/28/2025 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 3/11/2025 | Corrections Issued | EVAN COOPER |
| Deputy Reinf. Concrete | 3/12/2025 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 5/27/2025 | Approved | BOBBY KEY |
| HVAC-Rough | 5/27/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 5/27/2025 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 5/29/2025 | Corrections Issued | ARAM AVEDISIAN |
| Shower Pan | 5/29/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/30/2025 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 6/6/2025 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Conditional Approval | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 6/16/2025 | Approved | ARAM AVEDISIAN |
| Insulation | 6/24/2025 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 7/8/2025 | Approved | EVAN COOPER |
| Green Building Rough | 7/8/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/8/2025 | Approved | EVAN COOPER |
| METHANE-Rough | 7/8/2025 | Approved | EVAN COOPER |
| Insulation | 7/17/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 7/31/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 3/17/2026 | Approved | WILBER ROSALES |
| HVAC-Final | 3/17/2026 | Approved | WILBER ROSALES |
| Service/Power Release | 3/17/2026 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Final | 3/19/2026 | Approved | WILBER ROSALES |
| Final | 3/24/2026 | Corrections Issued | WILBER ROSALES |
| Footing/Foundation/Slab | 3/24/2026 | Approved | WILBER ROSALES |
| Green Building Final | 3/24/2026 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 3/24/2026 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 3/24/2026 | Approved | WILBER ROSALES |
| Final | 5/11/2026 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 5/11/2026 | Approved | KIRK SANDERS |