8833 W CASHIO ST 90035

Certificate Information: 8833 W CASHIO ST 90035

Application / Permit
24014-10000-02883
Plan Check / Job No.
B24LA12641
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: MAJOR REMODEL AND BASEMENT ADDIITION TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 12/4/2024
Issuing Office
Current Status
CofO Issued on 5/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2024 APPLICANT
Assigned to Plan Check Engineer 7/3/2024 DANIEL YIP
Corrections Issued 7/6/2024 DANIEL YIP
Quality Review Completed 7/31/2024 PRANITA SHAH
Applicant returned to address corrections 12/3/2024 DANIEL YIP
Plan Check Approved 12/4/2024 DANIEL YIP
Issued 12/4/2024 APPLICANT
CofO in Progress 5/12/2026 KIRK SANDERS
Permit Finaled 5/22/2026 RICHARD STEINBACH
CofO Issued 5/22/2026 RICHARD STEINBACH
Permit Finaled 5/22/2026 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 8/7/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/9/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 9/3/2024 WALLIE JONG
Construction near power lines Cleared 9/23/2024 RIDWAN HARDY
Construction within easement Cleared 9/23/2024 RIDWAN HARDY
Sewer availability Cleared 9/23/2024 WALLIE JONG
Trees in Parkway Cleared 10/1/2024 DYNL MIRANDA
Hydrant and Access approval Cleared 10/17/2024 JERRY KAO
GPI Written Notices Cleared 12/3/2024 DANIEL YIP
Grading Pre-Inspection Cleared 12/3/2024 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/12/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 1/13/2025 Partial Approval MEL KHACHATOURIAN
METHANE-Barrier 1/16/2025 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Rough 1/16/2025 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Subgrade 1/16/2025 Approved MEL KHACHATOURIAN
Deputy Methane Barrier 1/23/2025 No Access for Inspection MEL KHACHATOURIAN
METHANE-Barrier 1/23/2025 Approved MEL KHACHATOURIAN
METHANE-Rough 1/23/2025 Not Ready for Inspection MEL KHACHATOURIAN
Deputy Reinf. Concrete 2/6/2025 No Access for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 2/6/2025 Partial Approval MEL KHACHATOURIAN
Deputy Reinf. Concrete 2/7/2025 No Access for Inspection MEL KHACHATOURIAN
Deputy Reinf. Concrete 2/19/2025 No Access for Inspection MEL KHACHATOURIAN
Deputy Shotcrete 2/19/2025 No Access for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 2/19/2025 Corrections Issued MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 2/20/2025 Approved MEL KHACHATOURIAN
METHANE-Final 2/28/2025 Not Ready for Inspection EVAN COOPER
METHANE-Rough 2/28/2025 Partial Approval EVAN COOPER
Footing/Foundation/Slab 3/11/2025 Corrections Issued EVAN COOPER
Deputy Reinf. Concrete 3/12/2025 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/27/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Partial Approval EVAN COOPER
ELECTRICAL-Rough 5/27/2025 Approved BOBBY KEY
HVAC-Rough 5/27/2025 Approved BOBBY KEY
PLUMBING-Rough 5/27/2025 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 5/29/2025 Corrections Issued ARAM AVEDISIAN
Shower Pan 5/29/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 5/30/2025 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 6/6/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/16/2025 Conditional Approval ARAM AVEDISIAN
Verify Sprinkler Sign Off 6/16/2025 Approved ARAM AVEDISIAN
Insulation 6/24/2025 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 7/8/2025 Approved EVAN COOPER
Green Building Rough 7/8/2025 Approved EVAN COOPER
Interior/Exterior Lathing 7/8/2025 Approved EVAN COOPER
METHANE-Rough 7/8/2025 Approved EVAN COOPER
Insulation 7/17/2025 Approved EVAN COOPER
Drywall Nailing 7/31/2025 Approved EVAN COOPER
ELECTRICAL-Final 3/17/2026 Approved WILBER ROSALES
HVAC-Final 3/17/2026 Approved WILBER ROSALES
Service/Power Release 3/17/2026 Not Ready for Inspection WILBER ROSALES
PLUMBING-Final 3/19/2026 Approved WILBER ROSALES
Final 3/24/2026 Corrections Issued WILBER ROSALES
Footing/Foundation/Slab 3/24/2026 Approved WILBER ROSALES
Green Building Final 3/24/2026 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Approved WILBER ROSALES
Smoke Detectors 3/24/2026 Approved WILBER ROSALES
Final 5/11/2026 OK to Issue CofO KIRK SANDERS
Service/Power Release 5/11/2026 Approved KIRK SANDERS