7950 S RAMSGATE AVE 90045

Certificate Information: 7950 S RAMSGATE AVE 90045

Application / Permit
24014-10000-02876
Plan Check / Job No.
B24LA12580
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition (98 SF) at front and Addition (145 SF) at rear of (E) Single Family Dwelling . Work per Architect/Engineer design .
Permit Issued
Issued on 8/25/2024
Issuing Office
Current Status
Issued on 8/25/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/2/2024 APPLICANT
Assigned to Plan Check Engineer 7/8/2024 ALEXANDER JOO
Corrections Issued 7/9/2024 ALEXANDER JOO
Plan Check Approved 8/15/2024 GEORGE ALVAREZ
Issued 8/25/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/23/2024 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 7/23/2024 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 7/26/2024 DARIN LAM
Specific Plan Cleared 8/14/2024 JOSHUA JONES

Contact Information

Architect Mizuki,, Steve Massanori; Lic. No.: NA22676       ,
Contractor Mikhail Designs; Lic. No.: 960313-B       ,
Engineer Mixter,, Thomas J; Lic. No.: C51041 2345 COUNTY RD 630      DEL RIO, TX 78840

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/2/2025 Partial Inspection JESUS PINEDA
Excavation/Setback/Form/Re-Bar 4/18/2025 Approved TEMISTOCLES CAAL
Footing/Foundation/Slab 4/18/2025 Approved TEMISTOCLES CAAL
Special/Order Compliance 4/18/2025 Partial Inspection JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 6/2/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 6/6/2025 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/17/2025 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 10/6/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 10/6/2025 Corrections Issued JESUS PINEDA
Sewer 10/6/2025 Approved JESUS PINEDA
Underground Mechanical 10/6/2025 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/22/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 10/22/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 12/4/2025 Corrections Issued JESUS PINEDA
HVAC-Rough 12/4/2025 Approved JESUS PINEDA
PLUMBING-Rough 12/4/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 12/12/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/6/2026 Approved JESUS PINEDA
Gas Test 1/6/2026 Partial Approval JESUS PINEDA
Interior/Exterior Lathing 1/16/2026 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 1/23/2026 Approved JESUS PINEDA
Green Building Rough 1/23/2026 Approved JESUS PINEDA
Insulation 1/29/2026 Approved JESUS PINEDA
Drywall Nailing 2/4/2026 Approved TEMISTOCLES CAAL
Final 2/4/2026 Corrections Issued TEMISTOCLES CAAL
Shower Pan 3/13/2026 Corrections Issued JESUS PINEDA
Shower Pan 3/18/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 3/27/2026 Approved ANTHONY EGSON
Special/Order Compliance 3/27/2026 Partial Inspection BOBBY KEY