1351 1/2 W 71ST ST 90044
Certificate Information: 1351 1/2 W 71ST ST 90044
- Application / Permit
- 24014-10000-02871
- Plan Check / Job No.
- B24LA12556
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-plan. (E) Garage of 324 Sq. Ft. to be converted into an ADU and an addition of 126 Sq. Ft. total ADU area 450 Sq. Ft. per LAMC 12.22 A.33(c)-(d) R3 occupancy
- Permit Issued
- Issued on 6/24/2025
- Issuing Office
- Current Status
- CofO Issued on 1/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2024 | SAMUEL GONZALEZ |
| Corrections Issued | 7/13/2024 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 10/9/2024 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 10/24/2024 | SAMUEL GONZALEZ |
| Plan Check Approved | 10/29/2024 | KELVIN CHUONG |
| Issued | 6/24/2025 | APPLICANT |
| CofO in Progress | 1/13/2026 | BARRY HACHE |
| Permit Finaled | 1/14/2026 | DEROLD HAUFF |
| Permit Finaled | 1/14/2026 | DEROLD HAUFF |
| CofO Issued | 1/14/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/4/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 9/4/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2024 | CELINA MORENO |
| Sewer availability | Cleared | 9/6/2024 | CELINA MORENO |
Contact Information
| Contractor | Pure Passion Builders Inc; Lic. No.: 1102664-B | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2025 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 7/10/2025 | Corrections Issued | BARRY HACHE |
| Underground Mechanical | 7/29/2025 | Partial Approval | RONNIE MEDINA |
| Footing/Foundation/Slab | 8/4/2025 | Corrections Issued | BARRY HACHE |
| Underground Mechanical | 8/4/2025 | Not Ready for Inspection | BARRY HACHE |
| Footing/Foundation/Slab | 8/8/2025 | Corrections Issued | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 8/14/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 8/20/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 8/20/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 8/20/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 8/26/2025 | Approved | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 8/26/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 9/3/2025 | Approved | BARRY HACHE |
| Green Building Rough | 9/3/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 9/3/2025 | Approved | BARRY HACHE |
| Insulation | 9/5/2025 | Partial Inspection | RAUL BARAJAS |
| Drywall Nailing | 9/10/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 9/10/2025 | Not Ready for Inspection | BARRY HACHE |
| Shower Pan | 9/10/2025 | Not Ready for Inspection | BARRY HACHE |
| Interior/Exterior Lathing | 9/17/2025 | Approved | BARRY HACHE |
| Shower Pan | 9/17/2025 | Corrections Issued | BARRY HACHE |
| Shower Pan | 9/18/2025 | Corrections Issued | BARRY HACHE |
| Shower Pan | 9/22/2025 | Approved | BARRY HACHE |
| Sewer | 10/28/2025 | Approved | BARRY HACHE |
| Underground Mechanical | 10/28/2025 | Not Ready for Inspection | BARRY HACHE |
| Underground Mechanical | 10/31/2025 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 11/20/2025 | Corrections Issued | BARRY HACHE |
| Final | 11/20/2025 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 11/20/2025 | Approved | BARRY HACHE |
| Green Building Final | 11/20/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 11/20/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Final | 11/20/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 12/5/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 12/5/2025 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 12/5/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 12/5/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 12/5/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 12/5/2025 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 12/5/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 1/8/2026 | Approved | BARRY HACHE |
| Final | 1/8/2026 | Corrections Issued | BARRY HACHE |
| Green Building Final | 1/8/2026 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 1/8/2026 | Approved | BARRY HACHE |
| PLUMBING-Final | 1/8/2026 | Approved | BARRY HACHE |
| Final | 1/12/2026 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 1/12/2026 | Approved | BARRY HACHE |
| Final | 1/13/2026 | OK to Issue CofO | BARRY HACHE |