3934 S 3RD AVE 90008

Certificate Information: 3934 S 3RD AVE 90008

Application / Permit
24014-10000-02870
Plan Check / Job No.
B24LA12555
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION TO SINGLE FAMILY RESIDENCE (634 SF) TO INCLUDE TWO BEDROOMS, ONE BATHROOM, AND CLOSETS.
Permit Issued
Issued on 7/11/2024
Issuing Office
Metro
Current Status
CofO Issued on 6/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2024 APPLICANT
Assigned to Plan Check Engineer 7/1/2024 SAMUEL GONZALEZ
Corrections Issued 7/2/2024 SAMUEL GONZALEZ
Building Plans Picked Up 7/5/2024 APPLICANT
Applicant returned to address corrections 7/10/2024 NEHEMIAS RAMOS
Plan Check Approved 7/11/2024 ALEXANDER JOO
Issued 7/11/2024 APPLICANT
CofO in Progress 5/14/2025 LUIS CASTRO
No Progress 5/18/2025 DEROLD HAUFF
CofO in Progress 5/18/2025 DEROLD HAUFF
Permit Finaled 6/22/2025 DEROLD HAUFF
CofO Issued 6/22/2025 DEROLD HAUFF
Permit Finaled 6/22/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/10/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 7/10/2024 JEANIE LAM
Sewer availability Cleared 7/10/2024 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/16/2024 Conditional Approval ANTHONY EGSON
Footing/Foundation/Slab 7/18/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 7/24/2024 Corrections Issued JOSE MACIAS
Excavation/Setback/Form/Re-Bar 7/26/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 7/26/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Partial Approval ANTHONY EGSON
PLUMBING-Rough 8/6/2024 Corrections Issued ANTHONY EGSON
Insulation 8/7/2024 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 10/11/2024 Corrections Issued ANTHONY EGSON
HVAC-Rough 10/11/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 10/11/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 10/21/2024 Approved BARRY HACHE
HVAC-Rough 10/21/2024 Approved BARRY HACHE
PLUMBING-Rough 10/21/2024 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Approved BARRY HACHE
BUILDING-Rough-Frame 11/4/2024 Approved BARRY HACHE
Green Building Rough 11/4/2024 Approved BARRY HACHE
Interior/Exterior Lathing 11/4/2024 Approved BARRY HACHE
Insulation 11/13/2024 Approved BARRY HACHE
Drywall Nailing 11/18/2024 Approved ALEX COLIN
Shower Pan 11/22/2024 Approved BARRY HACHE
Interior/Exterior Lathing 1/3/2025 Approved LUIS CASTRO
ELECTRICAL-Final 4/14/2025 Approved LUIS CASTRO
HVAC-Final 4/14/2025 Approved LUIS CASTRO
PLUMBING-Final 4/14/2025 Approved LUIS CASTRO
Final 4/30/2025 Corrections Issued LUIS CASTRO
Green Building Final 4/30/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 4/30/2025 Approved LUIS CASTRO
Final 5/13/2025 OK to Issue CofO LUIS CASTRO