2025 S PARNELL AVE 90025
Certificate Information: 2025 S PARNELL AVE 90025
- Application / Permit
- 24014-10000-02864
- Plan Check / Job No.
- B24LA12534
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: 433 SF EXISTING GARAGE CONVERSION + 205SF ADDITION TO ADU. (638SQFT) PER ORDINANCE
- Permit Issued
- Issued on 12/19/2024
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | KHUONG TRUONG |
| Corrections Issued | 7/19/2024 | KHUONG TRUONG |
| Quality Review Completed | 7/26/2024 | GARO TELMI |
| Plan Check Approved | 12/17/2024 | KHUONG TRUONG |
| Issued | 12/19/2024 | APPLICANT |
| CofO in Progress | 12/19/2025 | EVAN COOPER |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
| CofO Issued | 12/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/2/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2024 | DARIN LAM |
| Sewer availability | Cleared | 8/2/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 8/5/2024 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 8/8/2024 | VASIL MIHALEV |
| Specific Plan | Cleared | 8/28/2024 | HAMID GHAEMMAGHAMI |
| Construction near power lines | Cleared | 11/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xi,, Wang; Lic. No.: NA85148 | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 4/16/2025 | Approved | DANIEL VERA |
| Underground Mechanical | 4/16/2025 | Partial Approval | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 4/24/2025 | Approved | DANIEL VERA |
| Footing/Foundation/Slab | 4/24/2025 | Approved | DANIEL VERA |
| Gas Test | 5/2/2025 | Corrections Issued | DANIEL VERA |
| Underground Mechanical | 5/2/2025 | Partial Approval | DANIEL VERA |
| Underground Mechanical | 5/6/2025 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Corrections Issued | DANIEL VERA |
| Special/Order Compliance | 5/14/2025 | Corrections Issued | DANIEL VERA |
| Deputy Wood Construction | 5/15/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 6/2/2025 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Approved | DANIEL VERA |
| HVAC-Rough | 6/2/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 6/2/2025 | Approved | DANIEL VERA |
| Special/Order Compliance | 6/3/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 6/5/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 6/5/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 6/5/2025 | Not Ready for Inspection | DANIEL VERA |
| Interior/Exterior Lathing | 6/5/2025 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 6/6/2025 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 6/6/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 6/6/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/6/2025 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/12/2025 | Approved | DANIEL VERA |
| Insulation | 6/20/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 6/25/2025 | Approved | DANIEL VERA |
| Shower Pan | 6/27/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 7/2/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 11/18/2025 | Corrections Issued | DANIEL VERA |
| Final | 11/18/2025 | Corrections Issued | DANIEL VERA |
| Green Building Final | 11/18/2025 | Approved | DANIEL VERA |
| HVAC-Final | 11/18/2025 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 11/18/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 11/18/2025 | SGSOV Not Ready | DANIEL VERA |
| Smoke Detectors | 11/18/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 12/19/2025 | Approved | EVAN COOPER |
| Final | 12/19/2025 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 12/19/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 12/19/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Approved | EVAN COOPER |