2025 S PARNELL AVE 90025

Certificate Information: 2025 S PARNELL AVE 90025

Application / Permit
24014-10000-02864
Plan Check / Job No.
B24LA12534
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: 433 SF EXISTING GARAGE CONVERSION + 205SF ADDITION TO ADU. (638SQFT) PER ORDINANCE
Permit Issued
Issued on 12/19/2024
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 KHUONG TRUONG
Corrections Issued 7/19/2024 KHUONG TRUONG
Quality Review Completed 7/26/2024 GARO TELMI
Plan Check Approved 12/17/2024 KHUONG TRUONG
Issued 12/19/2024 APPLICANT
CofO in Progress 12/19/2025 EVAN COOPER
Permit Finaled 12/30/2025 RICHARD STEINBACH
CofO Issued 12/30/2025 RICHARD STEINBACH
Permit Finaled 12/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/2/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 8/2/2024 DARIN LAM
Sewer availability Cleared 8/2/2024 DARIN LAM
Roof/Waste drainage to street Cleared 8/5/2024 DARIN LAM
Grading Pre-Inspection Cleared 8/8/2024 VASIL MIHALEV
Specific Plan Cleared 8/28/2024 HAMID GHAEMMAGHAMI
Construction near power lines Cleared 11/9/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Xi,, Wang; Lic. No.: NA85148       ,

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/16/2025 Approved DANIEL VERA
Underground Mechanical 4/16/2025 Partial Approval DANIEL VERA
Excavation/Setback/Form/Re-Bar 4/24/2025 Approved DANIEL VERA
Footing/Foundation/Slab 4/24/2025 Approved DANIEL VERA
Gas Test 5/2/2025 Corrections Issued DANIEL VERA
Underground Mechanical 5/2/2025 Partial Approval DANIEL VERA
Underground Mechanical 5/6/2025 Partial Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Corrections Issued DANIEL VERA
Special/Order Compliance 5/14/2025 Corrections Issued DANIEL VERA
Deputy Wood Construction 5/15/2025 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 6/2/2025 Partial Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 6/2/2025 Approved DANIEL VERA
HVAC-Rough 6/2/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 6/2/2025 Approved DANIEL VERA
Special/Order Compliance 6/3/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 6/5/2025 Not Ready for Inspection DANIEL VERA
Green Building Rough 6/5/2025 Not Ready for Inspection DANIEL VERA
HVAC-Rough 6/5/2025 Not Ready for Inspection DANIEL VERA
Interior/Exterior Lathing 6/5/2025 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 6/6/2025 Partial Approval ARAM AVEDISIAN
Green Building Rough 6/6/2025 Approved ARAM AVEDISIAN
HVAC-Rough 6/6/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 6/6/2025 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 6/12/2025 Approved DANIEL VERA
Insulation 6/20/2025 Approved DANIEL VERA
Drywall Nailing 6/25/2025 Approved DANIEL VERA
Shower Pan 6/27/2025 Approved DANIEL VERA
Interior/Exterior Lathing 7/2/2025 Approved DANIEL VERA
ELECTRICAL-Final 11/18/2025 Corrections Issued DANIEL VERA
Final 11/18/2025 Corrections Issued DANIEL VERA
Green Building Final 11/18/2025 Approved DANIEL VERA
HVAC-Final 11/18/2025 Corrections Issued DANIEL VERA
PLUMBING-Final 11/18/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 11/18/2025 SGSOV Not Ready DANIEL VERA
Smoke Detectors 11/18/2025 Approved DANIEL VERA
ELECTRICAL-Final 12/19/2025 Approved EVAN COOPER
Final 12/19/2025 OK to Issue CofO EVAN COOPER
HVAC-Final 12/19/2025 Approved EVAN COOPER
PLUMBING-Final 12/19/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Approved EVAN COOPER