3757 S HALLDALE AVE 90018
Certificate Information: 3757 S HALLDALE AVE 90018
- Application / Permit
- 24014-10000-02847
- Plan Check / Job No.
- B24LA12444
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan 16'-0" X 14'-6" IRREGULAR SHAPED ADDITION TO (E) SFD. "COMPLY WITH DEPARTMENT ORDER effective date 05/29/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 7/19/2024
- Issuing Office
- Current Status
- CofO Issued on 4/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2024 | ISIS ARGUETA |
| Corrections Issued | 7/4/2024 | ISIS ARGUETA |
| Plan Check Approved | 7/18/2024 | NGHI SU |
| Issued | 7/19/2024 | APPLICANT |
| CofO in Progress | 7/25/2025 | JOHN PARKER |
| Permit Finaled | 4/16/2026 | CLAUDIO MORENO |
| CofO Issued | 4/16/2026 | CLAUDIO MORENO |
| Permit Finaled | 4/16/2026 | CLAUDIO MORENO |
Permit Application Clearance Information
| ZA Case | Cleared | 7/11/2024 | NATHAN ROMINE |
| ZA Case | Cleared | 7/11/2024 | NATHAN ROMINE |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/16/2024 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Armando; Lic. No.: C83911 | 2000 W LINCOLN AVE MONTEBELLO, CA 90640 |
Inspector Information
| JOHN PARKER, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICHAEL SERETTI, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| HECTOR RODRIGUEZ, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| BRUCE TODD, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAVIER RAMOS SR, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIAN PODPORA, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/29/2024 | Corrections Issued | JOHN PARKER |
| Deputy Drilled-In Anchors | 9/5/2024 | Approved | JOHN PARKER |
| BUILDING-Rough-Frame | 9/19/2024 | Approved | JOHN PARKER |
| Green Building Rough | 9/19/2024 | Approved | JOHN PARKER |
| PLUMBING-Rough | 9/26/2024 | Approved | JOHN PARKER |
| Wood Frame | 10/23/2024 | Approved | JOHN PARKER |
| ELECTRICAL-Rough | 10/30/2024 | Approved | JOHN PARKER |
| PLUMBING-Rough | 10/30/2024 | Approved | JOHN PARKER |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Approved | JOHN PARKER |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Approved | JOHN PARKER |
| Interior/Exterior Lathing | 11/12/2024 | Approved | JOHN PARKER |
| Insulation | 12/3/2024 | Approved | JOHN PARKER |
| Drywall Nailing | 12/18/2024 | Approved | JOHN PARKER |
| Shower Pan | 12/19/2024 | Approved | JOHN PARKER |
| Final | 1/30/2025 | Corrections Issued | JOHN PARKER |
| Footing/Foundation/Slab | 1/30/2025 | Approved | JOHN PARKER |
| Green Building Final | 1/30/2025 | Not Ready for Inspection | JOHN PARKER |
| SGSOV-Seismic Gas S/O Valve | 1/30/2025 | SGSOV Not Ready | JOHN PARKER |
| Smoke Detectors | 1/30/2025 | Not Ready for Inspection | JOHN PARKER |
| Green Building Final | 7/14/2025 | Approved | JOHN PARKER |
| Final | 7/17/2025 | Partial Approval | JOHN PARKER |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Approved | JOHN PARKER |
| Smoke Detectors | 7/17/2025 | Approved | JOHN PARKER |
| Final | 7/24/2025 | OK to Issue CofO | JOHN PARKER |