4419 S INGLEWOOD BLVD 90066

Certificate Information: 4419 S INGLEWOOD BLVD 90066

Application / Permit
24014-10000-02844
Plan Check / Job No.
B24LA12425
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: REMODEL OF EXISTING KITCHEN AND ADDITION OF UNCOVERED PORCH TO THE REAR OF THE HOUSE.
Permit Issued
Issued on 1/3/2025
Issuing Office
Current Status
Permit Finaled on 5/14/2025

Permit Application Status History

Submitted 6/28/2024 APPLICANT
Assigned to Plan Check Engineer 7/5/2024 MIROOSH KHACHATOORIAN
Corrections Issued 7/8/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 12/19/2024 MOHAMMAD ESMAILI
Plan Check Approved 12/26/2024 MOHAMMAD ESMAILI
Issued 1/3/2025 APPLICANT
Permit Finaled 5/14/2025 BOBBY KEY

Permit Application Clearance Information

ZA Case Cleared 12/20/2024 NATHAN ROMINE
ZA Case Cleared 12/20/2024 NATHAN ROMINE
ZA Case Cleared 12/20/2024 NATHAN ROMINE
ZA Case Cleared 12/20/2024 NATHAN ROMINE

Contact Information

Architect Nichols,, Mark; Lic. No.: C38099 824 ALDERDALE COURT      NEWBURY PARK, CA 91320
Architect Nichols,, Mark; Lic. No.: NA38099       ,
Contractor T H Oconnor Construction Inc; Lic. No.: 762763-B       ,
Engineer Castro,, Ivan; Lic. No.: C84846 750 OTAY LAKES ROAD   #202    CHULA VISTA, CA 91910
Engineer Castro,, Ivan; Lic. No.: NA84846       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/19/2025 Approved JESUS PINEDA
Deputy Drilled-In Anchors 2/21/2025 Conditional Approval DAVID FEILER
ELECTRICAL-Rough 2/28/2025 Approved BOBBY KEY
Footing/Foundation/Slab 2/28/2025 Approved BOBBY KEY
HVAC-Rough 2/28/2025 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 2/28/2025 Approved BOBBY KEY
PLUMBING-Rough 2/28/2025 Corrections Issued BOBBY KEY
Wood Frame 2/28/2025 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 3/4/2025 Approved JESUS PINEDA
HVAC-Rough 3/4/2025 Approved JESUS PINEDA
PLUMBING-Rough 3/4/2025 Approved JESUS PINEDA
Insulation 3/6/2025 Approved JESUS PINEDA
Drywall Nailing 3/18/2025 Approved RUBEN RIVAS
Special/Order Compliance 3/18/2025 Partial Inspection BOBBY KEY
Final 5/14/2025 Permit Finaled BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved BOBBY KEY
Smoke Detectors 5/14/2025 Approved BOBBY KEY