13838 W WEDDINGTON ST 91401
Certificate Information: 13838 W WEDDINGTON ST 91401
- Application / Permit
- 24014-10000-02816
- Plan Check / Job No.
- B24LA12336
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- ePlan. Remodel and Addition to existing Accessory Living Quarter
- Permit Issued
- Issued on 10/18/2024
- Issuing Office
- Current Status
- CofO Issued on 3/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2024 | AMY GUEVARRA |
| Corrections Issued | 7/11/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 7/24/2024 | AMY GUEVARRA |
| Plan Check Approved | 7/29/2024 | AMY GUEVARRA |
| Issued | 10/18/2024 | APPLICANT |
| CofO in Progress | 3/3/2026 | VINCENT HANLEY |
| Permit Finaled | 3/24/2026 | RUBEN SALAS |
| CofO Issued | 3/24/2026 | RUBEN SALAS |
| Permit Finaled | 3/24/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/18/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/18/2024 | BIAINA HARITUNIAN |
Contact Information
| Architect | Dellos,, Wendy Guadalupe; Lic. No.: C36239 | 10411 HASKELL AVENUE GRANADA HILLS, CA 91344 |
| Contractor | Progressive Designs Inc; Lic. No.: 724660-B | , |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 347 ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Dean,, Brian Thomas; Lic. No.: S6087 | 684 CLARION CT SAN LUIS OBISPO, CA 93401 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/24/2024 | Partial Inspection | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 12/18/2024 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 1/15/2025 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 1/31/2025 | Conditional Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 2/5/2025 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 2/5/2025 | Approved | RYAN SALAZAR |
| Deputy Wood Construction | 3/4/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Conditional Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/24/2025 | Partial Approval | RYAN SALAZAR |
| HVAC-Rough | 3/24/2025 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 3/24/2025 | Approved | RYAN SALAZAR |
| Insulation | 4/2/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/23/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 5/2/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/9/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 10/2/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 10/2/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 10/2/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 2/18/2026 | Approved | VINCENT HANLEY |
| Final | 2/18/2026 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 2/18/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/18/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 2/18/2026 | Approved | VINCENT HANLEY |
| Final | 3/3/2026 | OK to Issue CofO | VINCENT HANLEY |