1132 S DACOTAH ST 90023
Certificate Information: 1132 S DACOTAH ST 90023
- Application / Permit
- 24014-10000-02776
- Plan Check / Job No.
- B24LA12122
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW 22'6" x 21' ADDITION TO (E) DETACHED GARAGE AND CONVERT ONLY THE ADDITION PORTION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 8/28/2024
- Issuing Office
- Current Status
- CofO Issued on 12/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 6/28/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 8/21/2024 | MIROOSH KHACHATOORIAN |
| Issued | 8/28/2024 | APPLICANT |
| CofO in Progress | 12/26/2025 | FREDDIE RIVERA |
| Permit Finaled | 12/27/2025 | DEROLD HAUFF |
| CofO Issued | 12/27/2025 | DEROLD HAUFF |
| Permit Finaled | 12/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2024 | JESSICA OPINION |
| Construction near power lines | Cleared | 7/8/2024 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 7/8/2024 | JESSICA OPINION |
| ZI | Cleared | 7/24/2024 | YINGSHI HUANG |
| ZI | Cleared | 7/24/2024 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 7/25/2024 | DAVID LOPEZ |
| Grading Pre-Inspection | Cleared | 8/21/2024 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/20/2024 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 9/25/2024 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 10/15/2024 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 10/15/2024 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2024 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 10/15/2024 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 10/15/2024 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 10/15/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 10/15/2024 | Approved | FREDDIE RIVERA |
| Wood Frame | 10/23/2024 | Approved | JOHN QUINTANILLA |
| Insulation | 10/28/2024 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 10/28/2024 | Approved | LUIS CASTRO |
| Drywall Nailing | 10/31/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 10/31/2024 | Approved | FREDDIE RIVERA |
| Shower Pan | 10/31/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/7/2024 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 12/5/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/25/2025 | Approved | FREDDIE RIVERA |
| Final | 2/25/2025 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 2/25/2025 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 2/25/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 2/25/2025 | Approved | FREDDIE RIVERA |
| Final | 12/24/2025 | OK to Issue CofO | FREDDIE RIVERA |