5349 N BUFFALO AVE 91401
Certificate Information: 5349 N BUFFALO AVE 91401
- Application / Permit
- 24014-10000-02714
- Plan Check / Job No.
- B24LA11875
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **ePlan** Enclose (e) att. covered porch and breezeway and 1-story addition to (e) single story SFD w/attached garage and covered porch
- Permit Issued
- Issued on 9/26/2024
- Issuing Office
- Current Status
- CofO Issued on 6/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2024 | REZA HAGHIGHAT |
| Corrections Issued | 6/26/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 9/25/2024 | DAVID CASTILLO |
| Issued | 9/26/2024 | APPLICANT |
| CofO in Progress | 5/31/2025 | MISAEL ESPARZA |
| Permit Finaled | 6/24/2025 | RUBEN SALAS |
| CofO Issued | 6/24/2025 | RUBEN SALAS |
| Permit Finaled | 6/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2024 | BIAINA HARITUNIAN |
| Permit | Cleared | 7/26/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/26/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/13/2024 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 12/13/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 1/6/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 2/11/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 2/11/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/6/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 3/6/2025 | Approved | MISAEL ESPARZA |
| Insulation | 3/6/2025 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/6/2025 | Partial Approval | MISAEL ESPARZA |
| Insulation | 3/10/2025 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 3/11/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 3/18/2025 | Approved | MISAEL ESPARZA |
| Final | 5/30/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/30/2025 | Approved | MISAEL ESPARZA |
| Green Building Final | 5/30/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/30/2025 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 5/30/2025 | Approved | MISAEL ESPARZA |