7836 S HARVARD BLVD 90047

Certificate Information: 7836 S HARVARD BLVD 90047

Application / Permit
24014-10000-02700
Plan Check / Job No.
B24LA11816
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 162SF STORAGE AND 494SF ADDITION TO A DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) ; (E) 360SF GARAGE TO REMAIN
Permit Issued
Issued on 3/1/2025
Issuing Office
Current Status
CofO Issued on 12/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2024 APPLICANT
Assigned to Plan Check Engineer 6/26/2024 CARLOS MONTES
Corrections Issued 6/26/2024 CARLOS MONTES
Applicant returned to address corrections 7/9/2024 CARLOS MONTES
Applicant returned to address corrections 7/26/2024 TSE MING HUANG
Applicant returned to address corrections 8/16/2024 FERNANDO FLORES
Applicant returned to address corrections 11/25/2024 TSE MING HUANG
Applicant returned to address corrections 1/2/2025 SAMUEL GONZALEZ
Plan Check Approved 1/21/2025 ALEXANDER JOO
Issued 3/1/2025 APPLICANT
CofO in Progress 12/10/2025 SALVADOR MARTINEZ
Permit Finaled 12/16/2025 DEROLD HAUFF
CofO Issued 12/16/2025 DEROLD HAUFF
Permit Finaled 12/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/2/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 7/2/2024 JEANIE LAM
Construction near power lines Cleared 11/3/2024 TINA MIRANDA
Eng Process Fee Ord 176,300 Cleared 11/22/2024 JEANIE LAM
Sewer availability Cleared 11/22/2024 JEANIE LAM

Contact Information

Contractor Build Tuff Construction; Lic. No.: 1076283-B       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/24/2025 Approved WAYNE REGESTER
Deputy Drilled-In Anchors 4/29/2025 Not Ready for Inspection WAYNE REGESTER
Excavation/Setback/Form/Re-Bar 5/1/2025 Order to Comply Issued WAYNE REGESTER
Footing/Foundation/Slab 5/1/2025 Approved WAYNE REGESTER
ELECTRICAL-Rough 6/10/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 6/10/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 6/12/2025 Approved WAYNE REGESTER
ELECTRICAL-Rough 6/12/2025 Approved WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Approved WAYNE REGESTER
Green Building Rough 6/12/2025 Approved WAYNE REGESTER
HVAC-Rough 6/12/2025 Approved WAYNE REGESTER
PLUMBING-Rough 6/12/2025 Approved WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 6/30/2025 Approved WAYNE REGESTER
PLUMBING-Rough 6/30/2025 Approved WAYNE REGESTER
Sewer 6/30/2025 Approved WAYNE REGESTER
Underground Mechanical 6/30/2025 Approved WAYNE REGESTER
Insulation 7/2/2025 Approved RONNIE MEDINA
Drywall Nailing 7/8/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 7/29/2025 Approved RONNIE MEDINA
Shower Pan 7/29/2025 Approved RONNIE MEDINA
ELECTRICAL-Final 8/19/2025 Not Ready for Inspection WAYNE REGESTER
Final 8/19/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 8/19/2025 Not Ready for Inspection WAYNE REGESTER
HVAC-Final 8/19/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Final 8/19/2025 Not Ready for Inspection WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Not Ready WAYNE REGESTER
Smoke Detectors 8/19/2025 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Final 8/21/2025 Approved WAYNE REGESTER
HVAC-Final 8/21/2025 Approved WAYNE REGESTER
PLUMBING-Final 8/21/2025 Approved WAYNE REGESTER
Final 11/5/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 11/5/2025 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV No Gas SALVADOR MARTINEZ
Smoke Detectors 11/5/2025 Approved SALVADOR MARTINEZ
Final 11/12/2025 Corrections Issued SALVADOR MARTINEZ
Final 12/1/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Final 12/9/2025 Approved SALVADOR MARTINEZ
Final 12/9/2025 OK to Issue CofO SALVADOR MARTINEZ
HVAC-Final 12/9/2025 Approved SALVADOR MARTINEZ
PLUMBING-Final 12/9/2025 Approved SALVADOR MARTINEZ