3899 N TOLAND WAY 90065

Certificate Information: 3899 N TOLAND WAY 90065

Application / Permit
24014-10000-02698
Plan Check / Job No.
B24LA11812
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF (E) GARAGE WITH NEW 1ST AND 2ND FLOOR ADDITION TO ADU PER LAMC 12.22 A.33 (c)-(d) -ADU SPRINKLERED THRU-OUT
Permit Issued
Issued on 8/19/2025
Issuing Office
Metro
Current Status
Issued on 8/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/18/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 MAHNAZ NOURHASHEMI
Corrections Issued 7/15/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 7/17/2024 KEN GILL
Building Plans Picked Up 7/25/2024 APPLICANT
Plan Check Approved 4/4/2025 MAHNAZ NOURHASHEMI
Issued 8/19/2025 APPLICANT

Permit Application Clearance Information

GPI Written Notices Cleared 7/15/2024 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 7/15/2024 MAHNAZ NOURHASHEMI
Address approval Cleared 9/12/2024 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 9/12/2024 ADRIAN SANCHEZ
Street Frontage Cleared 9/12/2024 ADRIAN SANCHEZ
Specific Plan Cleared 10/2/2024 ANDREA MAGANA-WITHERS
Eng Process Fee Ord 176,300 Cleared 10/4/2024 ADRIAN SANCHEZ
Sewer availability Cleared 10/4/2024 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 12/4/2024 KURT CORRAL
Miscellaneous Cleared 4/4/2025 ALBERT TAM

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/11/2026 Approved NICHOLAS LOPEZ
Footing/Foundation/Slab 2/11/2026 Approved NICHOLAS LOPEZ
PLUMBING-Rough 2/11/2026 Partial Approval NICHOLAS LOPEZ
ELECTRICAL-Rough 6/10/2026 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/10/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Rough 6/10/2026 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Rough 6/10/2026 Approved NICHOLAS LOPEZ
MERV13>=Rough 6/10/2026 Approved NICHOLAS LOPEZ
PLUMBING-Rough 6/10/2026 Approved NICHOLAS LOPEZ
Sewer 6/10/2026 Approved NICHOLAS LOPEZ
Underground Mechanical 6/10/2026 Partial Approval NICHOLAS LOPEZ