9629 W CRESTA DR 90035

Certificate Information: 9629 W CRESTA DR 90035

Application / Permit
24014-10000-02693
Plan Check / Job No.
B24LA11798
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN- 2ND STORY ADDITION AND MAJOR REMODEL TO EXISITNG SINGLE FAMILY DWELLING W/ATTACHED GARAGE -BLDG SPRINKLERED THRU-OUT
Permit Issued
Issued on 11/20/2024
Issuing Office
Current Status
CofO Issued on 10/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2024 APPLICANT
Assigned to Plan Check Engineer 6/19/2024 MAHNAZ NOURHASHEMI
Corrections Issued 6/23/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 6/25/2024 GARO TELMI
Applicant returned to address corrections 10/7/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 10/25/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 11/6/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 11/18/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 11/19/2024 MAHNAZ NOURHASHEMI
Issued 11/20/2024 APPLICANT
Permit Finaled 10/22/2025 RICHARD STEINBACH
CofO Issued 10/22/2025 RICHARD STEINBACH
Permit Finaled 10/22/2025 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 6/25/2024 HISASHI KOBAYAKAWA
Low Impact Development (LID) Cleared 7/15/2024 LUIS LUVANO
GPI Written Notices Cleared 7/17/2024 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 7/17/2024 MAHNAZ NOURHASHEMI
Roof/Waste drainage to street Cleared 8/6/2024 VLADIMIR ARUTYUNYAN
Trees in Parkway Cleared 8/8/2024 DYNL MIRANDA
Eng Process Fee Ord 176,300 Cleared 8/16/2024 KIMBERLY HERNANDEZ
Sewer availability Cleared 8/16/2024 KIMBERLY HERNANDEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/19/2024 Partial Inspection ARAM AVEDISIAN
PLUMBING-Rough 12/30/2024 Conditional Approval STEPHANIE SWANSON
Footing/Foundation/Slab 1/7/2025 Partial Approval BOBBY KEY
METHANE-Barrier 1/7/2025 Approved BOBBY KEY
METHANE-Subgrade 1/7/2025 Approved BOBBY KEY
Special/Order Compliance 1/7/2025 Partial Inspection JAYLIN GRAVITTE
Deputy Drilled-In Anchors 1/21/2025 Conditional Approval BOBBY KEY
Deputy Methane Barrier 1/21/2025 Approved EVAN COOPER
Footing/Foundation/Slab 1/21/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/3/2025 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Conditional Approval ARAM AVEDISIAN
Pre-Inspection 2/11/2025 Partial Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 3/11/2025 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Rough 3/11/2025 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 3/11/2025 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 3/21/2025 Approved ASHLEY THOMPSON
HVAC-Rough 3/21/2025 Partial Approval ASHLEY THOMPSON
PLUMBING-Rough 3/21/2025 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 4/24/2025 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Partial Approval ASHLEY THOMPSON
Green Building Rough 4/24/2025 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Rough 4/24/2025 Not Ready for Inspection ASHLEY THOMPSON
Sewer 4/24/2025 Approved ASHLEY THOMPSON
Underground Mechanical 4/24/2025 Partial Approval ASHLEY THOMPSON
Verify Sprinkler Sign Off 4/24/2025 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 5/1/2025 Partial Approval ASHLEY THOMPSON
Shower Pan 5/1/2025 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 5/2/2025 Corrections Issued ASHLEY THOMPSON
Green Building Rough 5/2/2025 Approved ASHLEY THOMPSON
METHANE-Rough 5/2/2025 Approved ASHLEY THOMPSON
Verify Sprinkler Sign Off 5/2/2025 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 5/7/2025 Approved MEL KHACHATOURIAN
Insulation 5/7/2025 Approved MEL KHACHATOURIAN
Drywall Nailing 5/15/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 5/15/2025 Approved ASHLEY THOMPSON
Gas Test 9/11/2025 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 9/11/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/11/2025 SGSOV Not Ready EVAN COOPER
HVAC-Final 9/16/2025 Conditional Approval MICHAEL ALLEN
ELECTRICAL-Final 9/18/2025 Corrections Issued ASHLEY THOMPSON
HVAC-Final 9/18/2025 Approved ASHLEY THOMPSON
ELECTRICAL-Final 9/24/2025 Approved ASHLEY THOMPSON
Final 9/30/2025 Corrections Issued ASHLEY THOMPSON
Green Building Final 9/30/2025 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 9/30/2025 SGSOV Not Ready ASHLEY THOMPSON
Smoke Detectors 9/30/2025 Approved ASHLEY THOMPSON
Final 10/9/2025 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved EVAN COOPER
Final 10/22/2025 Conditional Approval ASHLEY THOMPSON
Service/Power Release 10/22/2025 Approved ASHLEY THOMPSON