2938 S BENTLEY AVE 90064
Certificate Information: 2938 S BENTLEY AVE 90064
- Application / Permit
- 24014-10000-02674
- Plan Check / Job No.
- B24LA11700
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. 2 story addition to existing detached 2-car garage to create 2 story detached accessory dwelling unit with attached garage. ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 10/16/2025
- Issuing Office
- Current Status
- CofO in Progress on 6/2/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2024 | JAD BASMA |
| Corrections Issued | 7/17/2024 | JAD BASMA |
| Quality Review Completed | 7/19/2024 | GARO TELMI |
| Applicant returned to address corrections | 10/30/2024 | JAD BASMA |
| Plan Check Approved | 11/4/2024 | JAD BASMA |
| Issued | 10/16/2025 | APPLICANT |
| CofO in Progress | 6/2/2026 | ARAM AVEDISIAN |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2024 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2024 | DINAH GARIN |
| Sewer availability | Cleared | 7/31/2024 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 8/5/2024 | DINAH GARIN |
| Specific Plan | Cleared | 8/14/2024 | FREDDY GARCIA |
| Construction near power lines | Cleared | 10/24/2024 | TINA MIRANDA |
| GPI Written Notices | Cleared | 11/4/2024 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 11/4/2024 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: NA87675 | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/7/2026 | Partial Inspection | KIRK SANDERS |
| Deputy Drilled-In Anchors | 1/14/2026 | Conditional Approval | DAVID FEILER |
| Underground Mechanical | 1/14/2026 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 1/16/2026 | Approved | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 1/20/2026 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Rough | 2/10/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 2/10/2026 | Partial Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 2/10/2026 | Partial Inspection | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 2/17/2026 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 3/2/2026 | Corrections Issued | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2026 | Approved | WILBER ROSALES |
| HVAC-Rough | 3/2/2026 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 3/2/2026 | Approved | WILBER ROSALES |
| ELECTRICAL-Rough | 3/6/2026 | Corrections Issued | WILBER ROSALES |
| Wood Frame | 3/6/2026 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 3/11/2026 | Conditional Approval | ARAM AVEDISIAN |
| Green Building Rough | 3/11/2026 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/11/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| MERV13>=Rough | 3/11/2026 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/13/2026 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/13/2026 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/13/2026 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 3/19/2026 | Approved | RYAN SALAZAR |
| Sewer | 3/19/2026 | Approved | RYAN SALAZAR |
| Underground Mechanical | 3/19/2026 | Approved | RYAN SALAZAR |
| Drywall Nailing | 3/26/2026 | Conditional Approval | MICHAEL ALLEN |
| Shower Pan | 3/26/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 4/8/2026 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 5/29/2026 | Not Ready for Inspection | KIRK SANDERS |
| Final | 5/29/2026 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Final | 5/29/2026 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 5/29/2026 | Not Ready for Inspection | KIRK SANDERS |
| MERV13>=Final | 5/29/2026 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 5/29/2026 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Not Ready | KIRK SANDERS |
| Service/Power Release | 5/29/2026 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 5/29/2026 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 6/2/2026 | Approved | ARAM AVEDISIAN |
| Final | 6/2/2026 | OK to Issue CofO | ARAM AVEDISIAN |
| Gas Test | 6/2/2026 | Approved | ARAM AVEDISIAN |
| Green Building Final | 6/2/2026 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 6/2/2026 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 6/2/2026 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 6/2/2026 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/2/2026 | SGSOV Approved | ARAM AVEDISIAN |