2938 S BENTLEY AVE 90064

Certificate Information: 2938 S BENTLEY AVE 90064

Application / Permit
24014-10000-02674
Plan Check / Job No.
B24LA11700
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. 2 story addition to existing detached 2-car garage to create 2 story detached accessory dwelling unit with attached garage. ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 10/16/2025
Issuing Office
Current Status
CofO in Progress on 6/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/20/2024 APPLICANT
Assigned to Plan Check Engineer 7/11/2024 JAD BASMA
Corrections Issued 7/17/2024 JAD BASMA
Quality Review Completed 7/19/2024 GARO TELMI
Applicant returned to address corrections 10/30/2024 JAD BASMA
Plan Check Approved 11/4/2024 JAD BASMA
Issued 10/16/2025 APPLICANT
CofO in Progress 6/2/2026 ARAM AVEDISIAN

Permit Application Clearance Information

Address approval Cleared 7/26/2024 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/31/2024 DINAH GARIN
Sewer availability Cleared 7/31/2024 DINAH GARIN
Roof/Waste drainage to street Cleared 8/5/2024 DINAH GARIN
Specific Plan Cleared 8/14/2024 FREDDY GARCIA
Construction near power lines Cleared 10/24/2024 TINA MIRANDA
GPI Written Notices Cleared 11/4/2024 JAD BASMA
Grading Pre-Inspection Cleared 11/4/2024 JAD BASMA

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: NA87675       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/7/2026 Partial Inspection KIRK SANDERS
Deputy Drilled-In Anchors 1/14/2026 Conditional Approval DAVID FEILER
Underground Mechanical 1/14/2026 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 1/16/2026 Approved ARAM AVEDISIAN
Deputy Reinf. Concrete 1/20/2026 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 1/26/2026 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 2/10/2026 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 2/10/2026 Partial Inspection ARAM AVEDISIAN
PLUMBING-Rough 2/10/2026 Partial Inspection ARAM AVEDISIAN
Deputy Drilled-In Anchors 2/17/2026 Conditional Approval ANDREW NAVE
ELECTRICAL-Rough 3/2/2026 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 3/2/2026 Approved WILBER ROSALES
HVAC-Rough 3/2/2026 Approved WILBER ROSALES
PLUMBING-Rough 3/2/2026 Approved WILBER ROSALES
ELECTRICAL-Rough 3/6/2026 Corrections Issued WILBER ROSALES
Wood Frame 3/6/2026 Approved WILBER ROSALES
BUILDING-Rough-Frame 3/11/2026 Conditional Approval ARAM AVEDISIAN
Green Building Rough 3/11/2026 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 3/11/2026 Not Ready for Inspection ARAM AVEDISIAN
MERV13>=Rough 3/11/2026 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 3/13/2026 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 3/13/2026 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 3/13/2026 Partial Approval ARAM AVEDISIAN
Insulation 3/19/2026 Approved RYAN SALAZAR
Sewer 3/19/2026 Approved RYAN SALAZAR
Underground Mechanical 3/19/2026 Approved RYAN SALAZAR
Drywall Nailing 3/26/2026 Conditional Approval MICHAEL ALLEN
Shower Pan 3/26/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 4/8/2026 Approved RYAN SALAZAR
ELECTRICAL-Final 5/29/2026 Not Ready for Inspection KIRK SANDERS
Final 5/29/2026 Not Ready for Inspection KIRK SANDERS
Green Building Final 5/29/2026 Not Ready for Inspection KIRK SANDERS
HVAC-Final 5/29/2026 Not Ready for Inspection KIRK SANDERS
MERV13>=Final 5/29/2026 Not Ready for Inspection KIRK SANDERS
PLUMBING-Final 5/29/2026 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Not Ready KIRK SANDERS
Service/Power Release 5/29/2026 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 5/29/2026 Approved KIRK SANDERS
ELECTRICAL-Final 6/2/2026 Approved ARAM AVEDISIAN
Final 6/2/2026 OK to Issue CofO ARAM AVEDISIAN
Gas Test 6/2/2026 Approved ARAM AVEDISIAN
Green Building Final 6/2/2026 Approved ARAM AVEDISIAN
HVAC-Final 6/2/2026 Approved ARAM AVEDISIAN
MERV13>=Final 6/2/2026 Approved ARAM AVEDISIAN
PLUMBING-Final 6/2/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/2/2026 SGSOV Approved ARAM AVEDISIAN