11956 W VICTORIA AVE 90066

Certificate Information: 11956 W VICTORIA AVE 90066

Application / Permit
24014-10000-02653
Plan Check / Job No.
B24LA11657
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL/ADDITION TO EXISTING SFD WITH NEW ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 9/6/2024
Issuing Office
Current Status
CofO Issued on 6/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2024 APPLICANT
Assigned to Plan Check Engineer 6/19/2024 ARMEN JIVALAGIAN
Corrections Issued 6/25/2024 ARMEN JIVALAGIAN
Quality Review Completed 6/26/2024 PETER KIM
Applicant returned to address corrections 8/16/2024 ARMEN JIVALAGIAN
Plan Check Approved 9/6/2024 ARMEN JIVALAGIAN
Issued 9/6/2024 APPLICANT
CofO in Progress 6/16/2025 WILBER ROSALES
Permit Finaled 6/17/2025 RICHARD STEINBACH
CofO Issued 6/17/2025 RICHARD STEINBACH
Permit Finaled 6/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

Miscellaneous Cleared 7/5/2024 JAZMIN ROQUE
Miscellaneous Cleared 7/5/2024 JAZMIN ROQUE
Permit Cleared 7/5/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 7/8/2024 DARIN LAM
Sewer availability Cleared 7/8/2024 DARIN LAM
Grading Pre-Inspection Cleared 7/16/2024 VASIL MIHALEV
Low Impact Development (LID) Cleared 7/31/2024 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/6/2024 LIAM ODONOVAN
Specific Plan Cleared 8/6/2024 FREDDY GARCIA
Hydrant and Access approval Cleared 8/7/2024 GILBERT URREA
GPI Written Notices Cleared 8/16/2024 ARMEN JIVALAGIAN
Trees in Parkway Cleared 8/29/2024 MIGUEL ORNELAS

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: NA77737       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/20/2024 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 9/23/2024 Approved DANIEL VERA
Deputy Steel/Welding 9/26/2024 Conditional Approval DANIEL VERA
Underground Mechanical 10/1/2024 Approved DANIEL VERA
Wood Frame 10/1/2024 Approved DANIEL VERA
ELECTRICAL-Rough 10/2/2024 Partial Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Approved DANIEL VERA
Deputy Steel/Welding 10/9/2024 Conditional Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Approved DANIEL VERA
Deputy Wood Construction 10/30/2024 Conditional Approval REGINA MENDEZ
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Approved DANIEL VERA
HVAC-Rough 11/26/2024 Not Ready for Inspection DANIEL VERA
Interior/Exterior Lathing 11/26/2024 Partial Approval DANIEL VERA
PLUMBING-Rough 11/26/2024 Corrections Issued DANIEL VERA
ELECTRICAL-Rough 12/2/2024 Approved DANIEL VERA
HVAC-Rough 12/3/2024 Approved DANIEL VERA
PLUMBING-Rough 12/3/2024 Approved DANIEL VERA
BUILDING-Rough-Frame 12/12/2024 Not Ready for Inspection TEMISTOCLES CAAL
Green Building Rough 12/12/2024 Not Ready for Inspection TEMISTOCLES CAAL
BUILDING-Rough-Frame 12/16/2024 Corrections Issued DANIEL VERA
BUILDING-Rough-Frame 12/17/2024 Approved DANIEL VERA
Green Building Rough 12/17/2024 Approved DANIEL VERA
Insulation 12/19/2024 Approved DANIEL VERA
Drywall Nailing 12/24/2024 Approved DANIEL VERA
Shower Pan 12/24/2024 Approved DANIEL VERA
Interior/Exterior Lathing 12/27/2024 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 12/31/2024 Approved REGINA MENDEZ
Deputy Drilled-In Anchors 1/21/2025 Conditional Approval KIRK SANDERS
Footing/Foundation/Slab 1/21/2025 Corrections Issued KIRK SANDERS
Excavation/Setback/Form/Re-Bar 1/23/2025 Approved EVAN COOPER
HVAC-Final 4/16/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 4/16/2025 Corrections Issued WILBER ROSALES
ELECTRICAL-Final 4/21/2025 Approved WILBER ROSALES
Gas Test 4/21/2025 Approved WILBER ROSALES
Final 4/29/2025 Not Ready for Inspection WILBER ROSALES
Footing/Foundation/Slab 4/29/2025 Approved WILBER ROSALES
Green Building Final 4/29/2025 Not Ready for Inspection WILBER ROSALES
HVAC-Final 4/29/2025 Approved WILBER ROSALES
PLUMBING-Final 4/29/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 4/29/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 4/29/2025 Approved WILBER ROSALES
Sewer 5/20/2025 Approved WILBER ROSALES
Final 6/4/2025 Corrections Issued WILBER ROSALES
Green Building Final 6/4/2025 Approved WILBER ROSALES
Final 6/13/2025 OK to Issue CofO WILBER ROSALES
Service/Power Release 6/16/2025 Approved WILBER ROSALES