14626 W MORRISON ST 91403
Certificate Information: 14626 W MORRISON ST 91403
- Application / Permit
- 24014-10000-02648
- Plan Check / Job No.
- B24LA11632
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: (N) ADDITIONS AND REMODEL TO (E) SFD **NFPA-13D Fire Sprinklers Throughout**
- Permit Issued
- Issued on 8/29/2024
- Issuing Office
- Current Status
- CofO Issued on 12/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 6/22/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 8/9/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 8/14/2024 | ISIS ARGUETA |
| Plan Check Approved | 8/20/2024 | ISIS ARGUETA |
| Issued | 8/29/2024 | APPLICANT |
| CofO in Progress | 10/17/2025 | JACK KARGODORIAN |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
| CofO Issued | 12/26/2025 | RUBEN SALAS |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/23/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 7/23/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2024 | EDGAR ALCARAZ |
| ZI | Cleared | 8/8/2024 | ALEX VELA |
Contact Information
| Contractor | M General Construction; Lic. No.: 1077019-B | , |
| Engineer | Kim,, Hayne; Lic. No.: NA55742 | , |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/25/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 10/3/2024 | No Access for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 10/4/2024 | Partial Approval | VINCENT HANLEY |
| Wood Frame | 10/17/2024 | Partial Approval | JACK KARGODORIAN |
| Insulation | 10/21/2024 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2024 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 11/22/2024 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 1/24/2025 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 1/24/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 1/24/2025 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/24/2025 | No Access for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 2/24/2025 | No Access for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 2/24/2025 | No Access for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 3/10/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 3/17/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 3/17/2025 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/25/2025 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 3/25/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/25/2025 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/29/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 4/29/2025 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 4/29/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 4/29/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 5/16/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 5/20/2025 | Corrections Issued | JACK KARGODORIAN |
| Wood Frame | 5/22/2025 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 6/3/2025 | Approved | JACK KARGODORIAN |
| Shower Pan | 7/2/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 7/7/2025 | Partial Approval | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/3/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 10/8/2025 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 10/8/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Final | 10/8/2025 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/16/2025 | Approved | JACK KARGODORIAN |
| Final | 10/16/2025 | OK to Issue CofO | JACK KARGODORIAN |
| Footing/Foundation/Slab | 10/16/2025 | Approved | JACK KARGODORIAN |
| Green Building Final | 10/16/2025 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 10/16/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/16/2025 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 10/16/2025 | Approved | JACK KARGODORIAN |
| Smoke Detectors | 10/16/2025 | Approved | JACK KARGODORIAN |