7325-7327 N ENFIELD AVE 91335

Certificate Information: 7325-7327 N ENFIELD AVE 91335

Application / Permit
24014-10000-02642
Plan Check / Job No.
B24LA11612
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(ePLAN) Addition of 2-story accessory dwelling unit to existing 1-story single family dwelling with attached garage per LAMC 12.22 A.33 (c)-(d). All work per engineer details.
Permit Issued
Issued on 10/31/2024
Issuing Office
Current Status
CofO Issued on 3/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2024 APPLICANT
Assigned to Plan Check Engineer 6/19/2024 VICTOR CHEN
Corrections Issued 7/11/2024 VICTOR CHEN
Quality Review Completed 7/23/2024 YOUNG KIM
Applicant returned to address corrections 10/8/2024 VICTOR CHEN
Plan Check Approved 10/28/2024 VICTOR CHEN
Issued 10/31/2024 APPLICANT
CofO in Progress 2/10/2026 ARUTYUN MADATYAN
Permit Finaled 3/4/2026 JOHN JANSON
CofO Issued 3/4/2026 JOHN JANSON
Permit Finaled 3/4/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/23/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/23/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/25/2024 BIAINA HARITUNIAN
Sewer availability Cleared 9/25/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/3/2024 Conditional Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 12/11/2024 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 12/18/2024 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 12/26/2024 Approved ARUTYUN MADATYAN
Deputy Drilled-In Anchors 1/21/2025 Conditional Approval JUAN ALVARADO
Excavation/Setback/Form/Re-Bar 2/21/2025 Partial Inspection JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Corrections Issued JUAN ALVARADO
ELECTRICAL-Rough 4/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Rough 4/15/2025 No Access for Inspection ARUTYUN MADATYAN
HVAC-Rough 4/15/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 4/15/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/7/2025 Approved ROBERT GOLD
ELECTRICAL-Rough 7/7/2025 Approved ROBERT GOLD
Green Building Rough 7/7/2025 Approved ROBERT GOLD
HVAC-Rough 7/7/2025 Partial Approval ROBERT GOLD
Interior/Exterior Lathing 7/7/2025 Partial Approval ROBERT GOLD
Shower Pan 7/7/2025 Approved ROBERT GOLD
Insulation 7/15/2025 Approved JUAN ALVARADO
Drywall Nailing 7/25/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 12/4/2025 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 12/4/2025 Partial Approval ARUTYUN MADATYAN
Sewer 12/4/2025 Approved ARUTYUN MADATYAN
Final 2/2/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Final 2/2/2026 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 2/2/2026 SGSOV Not Ready ARUTYUN MADATYAN
Smoke Detectors 2/2/2026 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 2/10/2026 Approved ARUTYUN MADATYAN
Final 2/10/2026 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 2/10/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 2/10/2026 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 2/10/2026 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 2/10/2026 Approved ARUTYUN MADATYAN