3826 W BRUNSWICK AVE 90039
Certificate Information: 3826 W BRUNSWICK AVE 90039
- Application / Permit
- 24014-10000-02639
- Plan Check / Job No.
- B24LA11600
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. Addition to (E) SFD per engr's design
- Permit Issued
- Issued on 9/2/2024
- Issuing Office
- Current Status
- Issued on 9/2/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2024 | AMY GUEVARRA |
| Corrections Issued | 7/1/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 7/8/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 8/14/2024 | YASHAR EMAMI |
| Plan Check Approved | 8/28/2024 | YASHAR EMAMI |
| Issued | 9/2/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 7/5/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 7/5/2024 | JUSTIN BICOL |
Contact Information
| Architect | Verdugo,, Emilio Amado; Lic. No.: NA33263 | , |
| Contractor | Lydios Construction Inc; Lic. No.: 1007190-B | , |
| Engineer | Espino,, Manuel A; Lic. No.: NA55526 | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/8/2024 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/17/2024 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 11/7/2024 | Partial Approval | THOMAS LOGRASSO |
| Sewer | 11/7/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Approved | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 3/19/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 4/4/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 4/21/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 5/7/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 6/25/2025 | Corrections Issued | DAVID WILLIAMS |
| Interior/Exterior Lathing | 6/30/2025 | Approved | REGINA MENDEZ |
| BUILDING-Rough-Frame | 8/26/2025 | Approved | NICHOLAS LOPEZ |
| Final | 8/26/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 8/26/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 8/26/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Green Building Rough | 8/26/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 8/26/2025 | Approved | NICHOLAS LOPEZ |
| Final | 9/9/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 9/9/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Approved | NICHOLAS LOPEZ |