10610 S GRAMERCY PL 90047
Certificate Information: 10610 S GRAMERCY PL 90047
- Application / Permit
- 24014-10000-02634
- Plan Check / Job No.
- B24LA11576
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan 2-Story Addition +covered patio to EXISTING 1-Story Single Family Dwelling
- Permit Issued
- Issued on 10/2/2024
- Issuing Office
- Current Status
- CofO Issued on 5/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2024 | KHUONG TRUONG |
| Corrections Issued | 6/26/2024 | KHUONG TRUONG |
| Quality Review Completed | 7/8/2024 | GARO TELMI |
| Applicant returned to address corrections | 8/1/2024 | KHUONG TRUONG |
| Plan Check Approved | 10/1/2024 | KHUONG TRUONG |
| Issued | 10/2/2024 | APPLICANT |
| No Progress | 5/7/2026 | RAUL BARAJAS |
| CofO in Progress | 5/7/2026 | RAUL BARAJAS |
| CofO in Progress | 5/15/2026 | RAUL BARAJAS |
| Permit Finaled | 5/16/2026 | DEROLD HAUFF |
| CofO Issued | 5/16/2026 | DEROLD HAUFF |
| Permit Finaled | 5/16/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/2/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 7/3/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: NA5524 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/4/2024 | Not Ready for Inspection | LUIS CASTRO |
| Pre-Inspection | 10/4/2024 | Approved | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 10/8/2024 | Corrections Issued | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 10/10/2024 | Approved | AMIR NAZARIAN |
| Deputy Reinf. Concrete | 10/17/2024 | Conditional Approval | JOSH MEISTER |
| Wood Frame | 10/17/2024 | Partial Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Corrections Issued | AMIR NAZARIAN |
| Wood Frame | 12/16/2024 | Corrections Issued | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Partial Approval | AMIR NAZARIAN |
| PLUMBING-Rough | 12/23/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 1/13/2025 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 1/13/2025 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 1/13/2025 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/17/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 1/17/2025 | Partial Approval | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 1/17/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| METHANE-Rough | 1/17/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 1/17/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 1/22/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 1/22/2025 | Not Ready for Inspection | BARRY HACHE |
| Shower Pan | 1/22/2025 | Not Ready for Inspection | BARRY HACHE |
| Drywall Nailing | 1/27/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 1/27/2025 | Corrections Issued | ANTHONY RAMOS |
| Shower Pan | 1/27/2025 | Not Ready for Inspection | ANTHONY RAMOS |
| Interior/Exterior Lathing | 1/28/2025 | Partial Approval | ANTHONY RAMOS |
| Shower Pan | 1/28/2025 | Corrections Issued | ANTHONY RAMOS |
| Shower Pan | 2/11/2025 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 3/28/2025 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 2/24/2026 | Approved | SALVADOR MARTINEZ |
| Final | 2/24/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 2/24/2026 | Approved | SALVADOR MARTINEZ |
| Green Building Final | 2/24/2026 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 2/24/2026 | Approved | SALVADOR MARTINEZ |
| METHANE-Barrier | 2/24/2026 | Approved | SALVADOR MARTINEZ |
| METHANE-Subgrade | 2/24/2026 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 2/24/2026 | Approved | SALVADOR MARTINEZ |
| Final | 5/5/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 5/15/2026 | Conditional Approval | RAUL BARAJAS |
| Final | 5/15/2026 | OK to Issue CofO | RAUL BARAJAS |
| METHANE-Final | 5/15/2026 | Approved | RAUL BARAJAS |