3255 S MIDVALE AVE 90034
Certificate Information: 3255 S MIDVALE AVE 90034
- Application / Permit
- 24014-10000-02631
- Plan Check / Job No.
- B24LA11566
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN -INTERIOR REMODEL AND TWO STORY ADDITION TO EXISTING SPLIT-STORY SINGLE FAMILY RESIDENCE WITH AN ATTACHED GARAGE NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 12/31/2024
- Issuing Office
- Current Status
- Issued on 12/31/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2024 | JAD BASMA |
| Corrections Issued | 6/29/2024 | JAD BASMA |
| Quality Review Completed | 7/15/2024 | MICHAEL PEREZ |
| Applicant returned to address corrections | 11/21/2024 | JAD BASMA |
| Applicant returned to address corrections | 12/3/2024 | JAD BASMA |
| Plan Check Approved | 12/5/2024 | JAD BASMA |
| Issued | 12/31/2024 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/19/2024 | JULISSA LOPEZ-HODOYAN |
| Specific Plan | Cleared | 8/21/2024 | PEDRO AYALA |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2024 | DARIN LAM |
| Sewer availability | Cleared | 8/26/2024 | DARIN LAM |
| Trees in Parkway | Cleared | 8/26/2024 | ADALBERTO VERA |
| Permit | Cleared | 9/9/2024 | DARIN LAM |
| Hydrant and Access approval | Cleared | 10/21/2024 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 11/7/2024 | DARIN LAM |
| GPI Written Notices | Cleared | 11/21/2024 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 12/5/2024 | JAD BASMA |
Contact Information
| Contractor | Arg Builders Inc; Lic. No.: 1033233-B | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Approved | DANIEL VERA |
| Footing/Foundation/Slab | 2/11/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Corrections Issued | DANIEL VERA |
| Special/Order Compliance | 3/3/2025 | Approved | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Rough | 3/21/2025 | Not Ready for Inspection | WILBER ROSALES |
| Special/Order Compliance | 3/21/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Wood Frame | 3/21/2025 | Not Ready for Inspection | WILBER ROSALES |
| Deputy Wood Construction | 3/26/2025 | Approved | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2025 | Partial Approval | WILBER ROSALES |
| Special/Order Compliance | 3/26/2025 | Partial Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Rough | 7/17/2025 | Corrections Issued | WILBER ROSALES |
| HVAC-Rough | 7/17/2025 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Rough | 7/17/2025 | Corrections Issued | WILBER ROSALES |
| ELECTRICAL-Rough | 7/29/2025 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2025 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 7/29/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/29/2025 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/4/2025 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 8/4/2025 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 8/4/2025 | Partial Approval | KIRK SANDERS |
| Special/Order Compliance | 8/4/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 8/14/2025 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 8/20/2025 | No Access for Inspection | JAYLIN GRAVITTE |
| Final | 8/22/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Insulation | 8/22/2025 | Approved | JAYLIN GRAVITTE |
| Drywall Nailing | 9/2/2025 | Conditional Approval | KIRK SANDERS |
| Special/Order Compliance | 9/2/2025 | Corrections Issued | KIRK SANDERS |
| Shower Pan | 9/22/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 10/8/2025 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 10/15/2025 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Final | 10/15/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 10/15/2025 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 4/27/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV Approved | ASHLEY THOMPSON |
| Underground Mechanical | 4/27/2026 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 5/7/2026 | Approved | MICHAEL LEWIS |
| HVAC-Final | 5/7/2026 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 5/7/2026 | Corrections Issued | MICHAEL LEWIS |
| Special/Order Compliance | 5/7/2026 | Corrections Issued | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/13/2026 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 5/13/2026 | Approved | KIRK SANDERS |
| Final | 5/13/2026 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Final | 5/13/2026 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 5/13/2026 | Approved | KIRK SANDERS |
| HVAC-Final | 5/13/2026 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 5/13/2026 | Approved | KIRK SANDERS |
| Smoke Detectors | 5/13/2026 | Not Ready for Inspection | KIRK SANDERS |
| Service/Power Release | 5/29/2026 | Approved | BOBBY KEY |