10375 W ILONA AVE 90064

Certificate Information: 10375 W ILONA AVE 90064

Application / Permit
24014-10000-02591
Plan Check / Job No.
B24LA11383
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED ADDITION TO AND CONVERT THE (E) DETACHED GARAGE INTO A NEW ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) . SEE COMMENTS.
Permit Issued
Issued on 5/16/2025
Issuing Office
Current Status
CofO Issued on 9/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2024 APPLICANT
Assigned to Plan Check Engineer 6/18/2024 SARKIS HARABEDIAN
Corrections Issued 6/20/2024 SARKIS HARABEDIAN
Applicant returned to address corrections 1/15/2025 SARKIS HARABEDIAN
Plan Check Approved 1/26/2025 SARKIS HARABEDIAN
Issued 5/16/2025 APPLICANT
CofO in Progress 9/10/2025 DANIEL VERA
Permit Finaled 9/10/2025 RICHARD STEINBACH
Permit Finaled 9/10/2025 RICHARD STEINBACH
CofO Issued 9/10/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/16/2024 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 7/16/2024 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 7/25/2024 KIMBERLY HERNANDEZ
Sewer availability Cleared 7/25/2024 KIMBERLY HERNANDEZ
Specific Plan Cleared 8/12/2024 PEDRO AYALA
Grading Pre-Inspection Cleared 1/15/2025 SARKIS HARABEDIAN
Construction near power lines Cleared 1/23/2025 OSCAR CASTRO

Contact Information

Contractor Trumpower Development; Lic. No.: 1016132-B       ,
Engineer Ruvalcaba,, Martin Eduardo; Lic. No.: NA75838       ,

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/2/2025 Corrections Issued DANIEL VERA
Footing/Foundation/Slab 6/2/2025 Not Ready for Inspection DANIEL VERA
METHANE-Barrier 6/2/2025 Approved DANIEL VERA
METHANE-Subgrade 6/2/2025 Approved DANIEL VERA
PLUMBING-Rough 6/2/2025 Partial Approval DANIEL VERA
Excavation/Setback/Form/Re-Bar 6/4/2025 Approved DANIEL VERA
Footing/Foundation/Slab 6/4/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 6/13/2025 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Partial Approval DANIEL VERA
Green Building Rough 6/13/2025 Not Ready for Inspection DANIEL VERA
METHANE-Rough 6/13/2025 Approved DANIEL VERA
PLUMBING-Rough 6/13/2025 Approved DANIEL VERA
ELECTRICAL-Rough 6/18/2025 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Approved DANIEL VERA
Green Building Rough 6/18/2025 Not Ready for Inspection DANIEL VERA
HVAC-Rough 6/18/2025 Corrections Issued DANIEL VERA
HVAC-Rough 6/27/2025 Not Ready for Inspection DANIEL VERA
Sewer 6/27/2025 Approved DANIEL VERA
Shower Pan 6/27/2025 Approved DANIEL VERA
Underground Mechanical 6/27/2025 Corrections Issued DANIEL VERA
Green Building Rough 7/1/2025 Not Ready for Inspection DANIEL VERA
HVAC-Rough 7/1/2025 Approved DANIEL VERA
Interior/Exterior Lathing 7/1/2025 Approved DANIEL VERA
Underground Mechanical 7/1/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 7/8/2025 Approved DANIEL VERA
Green Building Rough 7/8/2025 Approved DANIEL VERA
Insulation 7/10/2025 Approved DANIEL VERA
Drywall Nailing 7/14/2025 Approved DANIEL VERA
ELECTRICAL-Final 8/19/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 8/27/2025 Approved DANIEL VERA
Green Building Final 9/4/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 9/4/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 9/4/2025 SGSOV Not Required DANIEL VERA
Smoke Detectors 9/4/2025 Approved DANIEL VERA
ELECTRICAL-Final 9/9/2025 Approved DANIEL VERA
Final 9/9/2025 OK to Issue CofO DANIEL VERA
Green Building Final 9/9/2025 Approved DANIEL VERA