400 S AVENUE 56 90042
Certificate Information: 400 S AVENUE 56 90042
- Application / Permit
- 24014-10000-02580
- Plan Check / Job No.
- B24LA11350
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 30'-9 1/2" X 24'-9" IRREGULAR SHAPED ADDITION AND REMODEL SINGLE FAMILY DWELLING - PER DESIGN **NFPA-13D FIRE SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 7/9/2024
- Issuing Office
- Current Status
- CofO Issued on 6/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 6/20/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 7/9/2024 | KAMYAR EMAMI |
| Issued | 7/9/2024 | APPLICANT |
| CofO in Progress | 6/25/2025 | LILIANA PORTILLO |
| Permit Finaled | 6/26/2025 | DEROLD HAUFF |
| Permit Finaled | 6/26/2025 | DEROLD HAUFF |
| CofO Issued | 6/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/21/2024 | DAVID VO |
| Sewer availability | Cleared | 6/26/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2024 | DAVID VO |
| Grading Pre-Inspection | Cleared | 6/27/2024 | CHARLES POWELL |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | My Home Builders Inc; Lic. No.: 1002927-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/26/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 9/24/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/11/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/21/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 11/4/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 11/19/2024 | Partial Approval | LILIANA PORTILLO |
| Wood Frame | 11/19/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/27/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Partial Approval | LILIANA PORTILLO |
| Insulation | 11/27/2024 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/22/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 1/22/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 1/22/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2025 | Partial Approval | LILIANA PORTILLO |
| MERV13>=Rough | 1/29/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 1/29/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/19/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 2/19/2025 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/26/2025 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/3/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 3/3/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/5/2025 | Conditional Approval | LILIANA PORTILLO |
| Rough-Elec/Plmb/HVAC | 3/5/2025 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 3/5/2025 | Approved | LILIANA PORTILLO |
| Insulation | 3/10/2025 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 3/12/2025 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 3/25/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 3/25/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/2/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/11/2025 | Approved | LILIANA PORTILLO |
| Final | 6/11/2025 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 6/11/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| MERV13>=Final | 6/11/2025 | Approved | LILIANA PORTILLO |
| MERV13>=Rough | 6/11/2025 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 6/11/2025 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 6/11/2025 | Corrections Issued | LILIANA PORTILLO |
| Final | 6/16/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 6/16/2025 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 6/16/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 6/24/2025 | Approved | LILIANA PORTILLO |
| Final | 6/24/2025 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 6/24/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 6/24/2025 | Approved | LILIANA PORTILLO |