1724 S FAIRFAX AVE 90019
Certificate Information: 1724 S FAIRFAX AVE 90019
- Application / Permit
- 24014-10000-02530
- Plan Check / Job No.
- B24LA11140
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Exterior/Interior Remodel to (E) SFD to remove enclosed patio cover [16'-0" x 16'-6"] (264 SF) at rear, and frame new [13'-6" x 18'-6"] (250 SF) Addition at rear . Addition is for proposed primary bedroom / primary bathroom / primary closet .
- Permit Issued
- Issued on 8/27/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 6/15/2024 | LAWRENCE QUIRANTE |
| Plan Check Approved | 7/19/2024 | GEORGE ALVAREZ |
| Issued | 8/27/2024 | APPLICANT |
| CofO in Progress | 1/7/2026 | BRENDAN MORELLI |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
| CofO Issued | 1/9/2026 | DEROLD HAUFF |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/18/2024 | OSCAR CASTRO |
| Roof/Waste drainage to street | Cleared | 7/12/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/15/2024 | Conditional Approval | ANTHONY RAMOS |
| Excavation/Setback/Form/Re-Bar | 10/24/2024 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 12/2/2024 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2024 | Approved | ARTHUR NEGRETE |
| Wood Frame | 12/5/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 1/24/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 1/24/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| PLUMBING-Rough | 1/24/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 2/20/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 2/20/2025 | Partial Approval | ALEX COLIN |
| Drywall Nailing | 3/5/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 3/18/2025 | Approved | ARTHUR NEGRETE |
| Shower Pan | 3/18/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 7/30/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/30/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 7/30/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 7/30/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 7/30/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Barrier | 7/30/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Final | 7/30/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Rough | 7/30/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Subgrade | 7/30/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/30/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/14/2025 | Corrections Issued | ARTHUR NEGRETE |
| Green Building Final | 8/14/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 8/29/2025 | Approved | ARTHUR NEGRETE |
| Green Building Final | 8/29/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 8/29/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 8/29/2025 | Approved | ARTHUR NEGRETE |
| Final | 1/7/2026 | OK to Issue CofO | BRENDAN MORELLI |