2043 N PARAMOUNT DR 90068
Certificate Information: 2043 N PARAMOUNT DR 90068
- Application / Permit
- 24014-10000-02490
- Plan Check / Job No.
- B24LA10600
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPALN 2ND STORY ACCESSORY DWELLING UNIT ADDITION TO (E) 2-CAR GARAGE SPRINKLERED NFPA13D THROUGH OUT ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 11/5/2024
- Issuing Office
- Current Status
- CofO Issued on 4/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | JAD BASMA |
| Corrections Issued | 6/9/2024 | JAD BASMA |
| Quality Review Completed | 6/26/2024 | MICHAEL PEREZ |
| Applicant returned to address corrections | 7/31/2024 | JAD BASMA |
| Applicant returned to address corrections | 11/4/2024 | JAD BASMA |
| Plan Check Approved | 11/5/2024 | JAD BASMA |
| Issued | 11/5/2024 | APPLICANT |
| CofO in Progress | 4/17/2026 | BRIAN SULLIVAN |
| Permit Finaled | 4/18/2026 | DEROLD HAUFF |
| CofO Issued | 4/18/2026 | DEROLD HAUFF |
| Permit Finaled | 4/18/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 7/3/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2024 | WALLIE JONG |
| Sewer availability | Cleared | 9/10/2024 | WALLIE JONG |
| GPI Written Notices | Cleared | 9/11/2024 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 9/11/2024 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: NA4978 | , |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2025 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 8/27/2025 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/30/2025 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/30/2025 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 9/30/2025 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 9/30/2025 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/30/2025 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 9/30/2025 | Corrections Issued | BRIAN SULLIVAN |
| Wood Frame | 9/30/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 11/6/2025 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 11/6/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 11/6/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 11/6/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/7/2025 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 11/7/2025 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 11/7/2025 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 11/12/2025 | Approved | ROY SPAULDING |
| Gas Test | 2/25/2026 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Not Ready | ROY SPAULDING |
| HVAC-Final | 3/17/2026 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 3/17/2026 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/13/2026 | SGSOV Not Ready | ROY SPAULDING |
| BUILDING-Rough-Frame | 4/15/2026 | Approved | ROY SPAULDING |
| Final | 4/15/2026 | Partial Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 4/15/2026 | Approved | ROY SPAULDING |
| Green Building Final | 4/15/2026 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/15/2026 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 4/15/2026 | Approved | ROY SPAULDING |
| Final | 4/16/2026 | Corrections Issued | ROY SPAULDING |
| Final | 4/17/2026 | OK to Issue CofO | BRIAN SULLIVAN |