308 N BRANCH ST 90042
Certificate Information: 308 N BRANCH ST 90042
- Application / Permit
- 24014-10000-02422
- Plan Check / Job No.
- B24LA10679
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- [ePlan] Remodel and 649 sf addition to (E) SFD and a new 93 SF attached patio cover
- Permit Issued
- Issued on 11/13/2024
- Issuing Office
- Current Status
- CofO Issued on 6/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 6/11/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 7/9/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 7/11/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 7/24/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 7/26/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 8/19/2024 | NEHEMIAS RAMOS |
| Issued | 11/13/2024 | APPLICANT |
| CofO in Progress | 6/13/2025 | DAVID WILLIAMS |
| Permit Finaled | 6/21/2025 | DEROLD HAUFF |
| Permit Finaled | 6/21/2025 | DEROLD HAUFF |
| CofO Issued | 6/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/17/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 7/18/2024 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 7/24/2024 | NEHEMIAS RAMOS |
| GPI Written Notices | Cleared | 8/16/2024 | NEHEMIAS RAMOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/26/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 12/3/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/4/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 12/4/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Sewer | 12/4/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 12/5/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 12/5/2024 | Approved | ROY SPAULDING |
| Sewer | 12/5/2024 | Approved | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 12/10/2024 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/10/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 1/22/2025 | Corrections Issued | CRAIG DAVIS |
| HVAC-Rough | 1/22/2025 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Rough | 2/4/2025 | Approved | CRAIG DAVIS |
| HVAC-Rough | 2/4/2025 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/21/2025 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 2/21/2025 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/27/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 2/27/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 3/11/2025 | Approved | DAVID WILLIAMS |
| Insulation | 3/14/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 3/14/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 3/26/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 3/26/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 3/26/2025 | Not Ready for Inspection | REGINA MENDEZ |
| BUILDING-Rough-Frame | 5/28/2025 | Approved | LILIANA PORTILLO |
| Final | 5/28/2025 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 5/28/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 5/28/2025 | Approved | LILIANA PORTILLO |
| HVAC-Final | 5/30/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 5/30/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 6/3/2025 | Approved | DAVID WILLIAMS |
| Final | 6/11/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 6/11/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 6/11/2025 | Approved | DAVID WILLIAMS |
| Final | 6/13/2025 | OK to Issue CofO | DAVID WILLIAMS |