2045-2047 N PARAMOUNT DR 90068

Certificate Information: 2045-2047 N PARAMOUNT DR 90068

Application / Permit
24014-10000-02407
Plan Check / Job No.
B24LA10600
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN 2-STORY ADDITION AND REMODEL TO (E) 2-STORY DUPLEX WHICH CONSISTS OF 13.5 SQFT ADDITION TO FIRST FLOOR AND 224.5 SQFT ADDITION TO SECOND FLOOR
Permit Issued
Issued on 11/5/2024
Issuing Office
Current Status
CofO Issued on 4/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 JAD BASMA
Corrections Issued 6/9/2024 JAD BASMA
Quality Review Completed 6/26/2024 MICHAEL PEREZ
Applicant returned to address corrections 7/31/2024 JAD BASMA
Applicant returned to address corrections 11/4/2024 JAD BASMA
Plan Check Approved 11/5/2024 JAD BASMA
No Progress 11/5/2024 JAD BASMA
Plan Check Approved 11/5/2024 JAD BASMA
Issued 11/5/2024 APPLICANT
CofO in Progress 4/17/2026 BRIAN SULLIVAN
Permit Finaled 4/17/2026 DEROLD HAUFF
CofO Issued 4/17/2026 DEROLD HAUFF
Permit Finaled 4/17/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/3/2024 WALLIE JONG
Sewer availability Cleared 7/3/2024 WALLIE JONG
Hydrant and Access approval Cleared 9/5/2024 GILBERT URREA
Eng Process Fee Ord 176,300 Cleared 9/10/2024 WALLIE JONG
GPI Written Notices Cleared 11/4/2024 JAD BASMA
Grading Pre-Inspection Cleared 11/4/2024 JAD BASMA

Contact Information

Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: NA4978       ,

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/7/2025 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 1/29/2025 Corrections Issued ROY SPAULDING
Pre-Inspection 1/31/2025 Corrections Issued ROY SPAULDING
Deputy Drilled-In Anchors 3/25/2025 Conditional Approval BRIAN SULLIVAN
Footing/Foundation/Slab 4/10/2025 Partial Approval CRAIG VAUGHAN
Piling/Pier/Caisson 4/10/2025 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Not Ready for Inspection CRAIG VAUGHAN
Deputy Wood Construction 6/16/2025 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 8/27/2025 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 9/26/2025 Approved CRAIG VAUGHAN
HVAC-Rough 9/26/2025 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 9/26/2025 Partial Approval CRAIG VAUGHAN
Wood Frame 9/26/2025 Approved CRAIG VAUGHAN
Insulation 10/7/2025 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 10/7/2025 Partial Approval BRIAN SULLIVAN
Shower Pan 10/7/2025 Approved BRIAN SULLIVAN
Drywall Nailing 10/17/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 10/17/2025 Approved DAVID WILLIAMS
ELECTRICAL-Final 2/4/2026 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Not Ready ROY SPAULDING
Gas Test 3/17/2026 Approved CRAIG VAUGHAN
HVAC-Final 3/17/2026 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 3/17/2026 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/13/2026 SGSOV Not Ready ROY SPAULDING
BUILDING-Rough-Frame 4/15/2026 Approved ROY SPAULDING
Final 4/15/2026 Partial Approval ROY SPAULDING
Footing/Foundation/Slab 4/15/2026 Approved ROY SPAULDING
Green Building Final 4/15/2026 Approved ROY SPAULDING
Green Building Rough 4/15/2026 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Approved ROY SPAULDING
Smoke Detectors 4/15/2026 Approved ROY SPAULDING
Final 4/16/2026 Conditional Approval ROY SPAULDING
Final 4/17/2026 OK to Issue CofO BRIAN SULLIVAN