14800 W MCCORMICK ST 91411
Certificate Information: 14800 W MCCORMICK ST 91411
- Application / Permit
- 24014-10000-02344
- Plan Check / Job No.
- B24LA10368
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ADDITION TO (E) SFD (1-STORY)
- Permit Issued
- Issued on 11/11/2024
- Issuing Office
- Current Status
- Issued on 11/11/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2024 | JOSE VELAZQUEZ |
| Corrections Issued | 6/6/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 7/17/2024 | ADAM HEGAZI |
| Plan Check Approved | 7/31/2024 | CARLOS MONTES |
| Issued | 11/11/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/11/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/11/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: NA55526 | , |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 11/12/2024 | Corrections Issued | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 11/21/2024 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 11/21/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 11/21/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Sewer | 11/21/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 4/4/2025 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 1/26/2026 | Not Ready for Inspection | VINCENT HANLEY |
| Wood Frame | 1/26/2026 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 2/17/2026 | Conditional Approval | RAUL OLAGI |
| Wood Frame | 2/19/2026 | Corrections Issued | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 2/24/2026 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 3/3/2026 | Corrections Issued | MICHAEL CORTEZ |
| HVAC-Rough | 3/3/2026 | Corrections Issued | MICHAEL CORTEZ |
| PLUMBING-Rough | 3/3/2026 | Conditional Approval | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 3/5/2026 | Not Ready for Inspection | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 3/5/2026 | Approved | MICHAEL CORTEZ |
| HVAC-Rough | 3/5/2026 | Approved | MICHAEL CORTEZ |
| Verify Sprinkler Sign Off | 3/5/2026 | Not Ready for Inspection | MICHAEL CORTEZ |
| Wood Frame | 3/5/2026 | Partial Approval | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 4/8/2026 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/22/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 5/22/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 5/22/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 5/22/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 5/22/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/22/2026 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 5/22/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 5/22/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 5/28/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Sewer | 5/28/2026 | Approved | NICHOLAS TROWBRIDGE |