7255-7257 W 91ST ST 90045

Certificate Information: 7255-7257 W 91ST ST 90045

Application / Permit
24014-10000-02313
Plan Check / Job No.
B24LA10235
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPlan Convert attached (E) 2-Car Garage into A.D.U per LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 10/10/2024
Issuing Office
Current Status
CofO Issued on 5/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2024 APPLICANT
Assigned to Plan Check Engineer 6/4/2024 SAMUEL GONZALEZ
Corrections Issued 6/4/2024 SAMUEL GONZALEZ
Applicant returned to address corrections 7/3/2024 SAMUEL GONZALEZ
Plan Check Approved 7/10/2024 SAMUEL GONZALEZ
Issued 10/10/2024 APPLICANT
CofO in Progress 5/22/2026 MICHAEL LEWIS
Permit Finaled 5/23/2026 RICHARD STEINBACH
CofO Issued 5/23/2026 RICHARD STEINBACH
Permit Finaled 5/23/2026 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/10/2024 VASIL MIHALEV
Address approval Cleared 6/15/2024 LIAM ODONOVAN
Sewer availability Cleared 6/15/2024 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 6/24/2024 LIAM ODONOVAN

Contact Information

Contractor Hades Construction; Lic. No.: 1047035-B       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/10/2024 Approved TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 12/10/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 12/10/2024 Partial Approval TEMISTOCLES CAAL
Sewer 12/10/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 4/30/2025 Approved TEMISTOCLES CAAL
HVAC-Rough 4/30/2025 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 4/30/2025 Corrections Issued TEMISTOCLES CAAL
HVAC-Rough 6/23/2025 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 6/23/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 8/15/2025 Corrections Issued MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 8/15/2025 Approved MICHAEL ALLEN
HVAC-Rough 8/15/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 8/15/2025 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 9/11/2025 Approved MICHAEL ALLEN
Green Building Rough 9/11/2025 Approved MICHAEL ALLEN
Insulation 9/19/2025 Corrections Issued JAYLIN GRAVITTE
Drywall Nailing 9/26/2025 Corrections Issued JESUS PINEDA
Green Building Final 9/26/2025 Corrections Issued JESUS PINEDA
Insulation 9/26/2025 Approved JESUS PINEDA
Drywall Nailing 9/30/2025 Approved JESUS PINEDA
Shower Pan 10/22/2025 Approved JESUS RODRIGUEZ
Final 5/12/2026 Corrections Issued MICHAEL LEWIS
Green Building Final 5/12/2026 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 5/12/2026 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 5/12/2026 Approved MICHAEL LEWIS
Final 5/21/2026 OK to Issue CofO MICHAEL LEWIS
Green Building Final 5/21/2026 Approved MICHAEL LEWIS