7255-7257 W 91ST ST 90045
Certificate Information: 7255-7257 W 91ST ST 90045
- Application / Permit
- 24014-10000-02313
- Plan Check / Job No.
- B24LA10235
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPlan Convert attached (E) 2-Car Garage into A.D.U per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 10/10/2024
- Issuing Office
- Current Status
- CofO Issued on 5/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2024 | SAMUEL GONZALEZ |
| Corrections Issued | 6/4/2024 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 7/3/2024 | SAMUEL GONZALEZ |
| Plan Check Approved | 7/10/2024 | SAMUEL GONZALEZ |
| Issued | 10/10/2024 | APPLICANT |
| CofO in Progress | 5/22/2026 | MICHAEL LEWIS |
| Permit Finaled | 5/23/2026 | RICHARD STEINBACH |
| CofO Issued | 5/23/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/23/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/10/2024 | VASIL MIHALEV |
| Address approval | Cleared | 6/15/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 6/15/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2024 | LIAM ODONOVAN |
Contact Information
| Contractor | Hades Construction; Lic. No.: 1047035-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/10/2024 | Approved | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 12/10/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/10/2024 | Partial Approval | TEMISTOCLES CAAL |
| Sewer | 12/10/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 4/30/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 4/30/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/30/2025 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 6/23/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 6/23/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 8/15/2025 | Corrections Issued | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 8/15/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 8/15/2025 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 9/11/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 9/11/2025 | Approved | MICHAEL ALLEN |
| Insulation | 9/19/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Drywall Nailing | 9/26/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 9/26/2025 | Corrections Issued | JESUS PINEDA |
| Insulation | 9/26/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 9/30/2025 | Approved | JESUS PINEDA |
| Shower Pan | 10/22/2025 | Approved | JESUS RODRIGUEZ |
| Final | 5/12/2026 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 5/12/2026 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 5/12/2026 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 5/12/2026 | Approved | MICHAEL LEWIS |
| Final | 5/21/2026 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 5/21/2026 | Approved | MICHAEL LEWIS |