2032-2032 1/2 E 3RD ST 90033

Certificate Information: 2032-2032 1/2 E 3RD ST 90033

Application / Permit
24014-10000-02296
Plan Check / Job No.
B24LA10160
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan Convert attached garage with addition to new attached ADU to existing single family dwelling per ordinance. Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2).
Permit Issued
Issued on 7/17/2024
Issuing Office
Current Status
CofO Issued on 1/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2024 APPLICANT
Assigned to Plan Check Engineer 5/30/2024 JOHN MESIAS
Corrections Issued 5/30/2024 JOHN MESIAS
Applicant returned to address corrections 6/25/2024 SUNMIN LEE
Applicant returned to address corrections 7/4/2024 JOHN MESIAS
Applicant returned to address corrections 7/12/2024 ADAM HEGAZI
Plan Check Approved 7/17/2024 ADAM HEGAZI
Issued 7/17/2024 APPLICANT
CofO in Progress 1/9/2025 FREDDIE RIVERA
Permit Finaled 1/9/2025 DEROLD HAUFF
CofO Issued 1/9/2025 DEROLD HAUFF
Permit Finaled 1/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/31/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 5/31/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 5/31/2024 CHRISTINA BRACO
Sewer availability Cleared 5/31/2024 CHRISTINA BRACO
Clean Up Green Up Cleared 6/3/2024 JAZMIN ROQUE
Grading Pre-Inspection Cleared 7/4/2024 SUNMIN LEE

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Ha My Design, Inc; Lic. No.: 999603-B       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/30/2024 Partial Inspection FREDDIE RIVERA
METHANE-Barrier 7/30/2024 Approved FREDDIE RIVERA
METHANE-Subgrade 7/30/2024 Approved FREDDIE RIVERA
PLUMBING-Rough 7/30/2024 Partial Approval FREDDIE RIVERA
Underground Mechanical 7/30/2024 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 8/2/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 8/20/2024 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 8/20/2024 Approved FREDDIE RIVERA
Green Building Rough 8/20/2024 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 8/20/2024 Approved FREDDIE RIVERA
METHANE-Rough 8/20/2024 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 8/20/2024 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 8/23/2024 Approved LUIS CASTRO
BUILDING-Rough-Frame 8/29/2024 Approved FREDDIE RIVERA
Green Building Rough 8/29/2024 Approved FREDDIE RIVERA
HVAC-Rough 8/29/2024 Approved FREDDIE RIVERA
Interior/Exterior Lathing 8/29/2024 Approved FREDDIE RIVERA
METHANE-Rough 8/29/2024 Approved FREDDIE RIVERA
Shower Pan 8/29/2024 Approved FREDDIE RIVERA
Insulation 9/4/2024 Approved JUSTIN HAWLEY
Drywall Nailing 9/11/2024 Approved ANTHONY RAMOS
Final 11/8/2024 Partial Inspection FREDDIE RIVERA
Green Building Final 11/8/2024 Partial Inspection FREDDIE RIVERA
MERV13>=Final 11/8/2024 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 11/8/2024 Partial Inspection FREDDIE RIVERA
Smoke Detectors 11/8/2024 Partial Inspection FREDDIE RIVERA
Final 11/18/2024 Corrections Issued LUIS CASTRO
Green Building Final 11/18/2024 Approved LUIS CASTRO
MERV13>=Final 11/18/2024 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Approved LUIS CASTRO
Smoke Detectors 11/18/2024 Approved LUIS CASTRO
ELECTRICAL-Final 11/20/2024 Approved JOHN QUINTANILLA
HVAC-Final 11/20/2024 Approved JOHN QUINTANILLA
PLUMBING-Final 11/20/2024 Approved JOHN QUINTANILLA
Service/Power Release 11/22/2024 Approved JOHN QUINTANILLA
Final 1/9/2025 OK to Issue CofO FREDDIE RIVERA