5325 E BUCHANAN ST 90042

Certificate Information: 5325 E BUCHANAN ST 90042

Application / Permit
24014-10000-02287
Plan Check / Job No.
B24LA10117
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan REMODEL, GROUND FLOOR AND 2ND FLOOR ADDITION TO (E) 1-STORY SFD, WITH UNCOVERED DECK AT REAR.
Permit Issued
Issued on 11/14/2024
Issuing Office
Current Status
CofO Issued on 10/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2024 APPLICANT
Assigned to Plan Check Engineer 6/13/2024 ADRIANA LOPEZ
Corrections Issued 6/24/2024 ADRIANA LOPEZ
Quality Review Completed 7/5/2024 SINA KHOSRAVI
Applicant returned to address corrections 9/12/2024 ADRIANA LOPEZ
Applicant returned to address corrections 10/10/2024 ADRIANA LOPEZ
Applicant returned to address corrections 11/6/2024 ADRIANA LOPEZ
Plan Check Approved 11/13/2024 ADRIANA LOPEZ
Issued 11/14/2024 APPLICANT
CofO in Progress 10/3/2025 DAVID WILLIAMS
Permit Finaled 10/4/2025 DEROLD HAUFF
CofO Issued 10/4/2025 DEROLD HAUFF
Permit Finaled 10/4/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/8/2024 CELINA MORENO
Sewer availability Cleared 7/8/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/12/2024 CELINA MORENO
Grading Pre-Inspection Cleared 7/29/2024 ALEXANDER HELFER
GPI Written Notices Cleared 10/10/2024 ADRIANA LOPEZ

Contact Information

Contractor United Remodeling Construction Inc; Lic. No.: 813590-B       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: NA93095       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/11/2024 Approved ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 12/12/2024 Conditional Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 12/27/2024 Corrections Issued CRAIG DAVIS
Green Building Rough 12/27/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 12/27/2024 Corrections Issued CRAIG DAVIS
Insulation 12/30/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 1/3/2025 Conditional Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Partial Approval DAVID WILLIAMS
HVAC-Rough 3/6/2025 Corrections Issued DAVID WILLIAMS
PLUMBING-Rough 3/6/2025 Not Ready for Inspection DAVID WILLIAMS
BUILDING-Rough-Frame 5/21/2025 Not Ready for Inspection DAVID WILLIAMS
Green Building Rough 5/21/2025 Not Ready for Inspection DAVID WILLIAMS
HVAC-Rough 5/21/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 5/21/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 5/23/2025 Approved DAVID WILLIAMS
ELECTRICAL-Rough 5/23/2025 Approved DAVID WILLIAMS
Green Building Rough 5/23/2025 Approved DAVID WILLIAMS
Insulation 6/4/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 6/4/2025 Approved REGINA MENDEZ
Shower Pan 6/4/2025 Approved REGINA MENDEZ
Drywall Nailing 6/9/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 6/9/2025 Approved DAVID WILLIAMS
ELECTRICAL-Final 9/22/2025 Approved DAVID WILLIAMS
Final 9/22/2025 Corrections Issued DAVID WILLIAMS
Green Building Final 9/22/2025 Approved DAVID WILLIAMS
HVAC-Final 9/22/2025 Approved DAVID WILLIAMS
PLUMBING-Final 9/22/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 9/22/2025 SGSOV Approved DAVID WILLIAMS
Service/Power Release 9/22/2025 Approved DAVID WILLIAMS
Smoke Detectors 9/22/2025 Approved DAVID WILLIAMS
Final 10/3/2025 OK to Issue CofO DAVID WILLIAMS