5325 E BUCHANAN ST 90042
Certificate Information: 5325 E BUCHANAN ST 90042
- Application / Permit
- 24014-10000-02287
- Plan Check / Job No.
- B24LA10117
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan REMODEL, GROUND FLOOR AND 2ND FLOOR ADDITION TO (E) 1-STORY SFD, WITH UNCOVERED DECK AT REAR.
- Permit Issued
- Issued on 11/14/2024
- Issuing Office
- Current Status
- CofO Issued on 10/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | ADRIANA LOPEZ |
| Corrections Issued | 6/24/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 7/5/2024 | SINA KHOSRAVI |
| Applicant returned to address corrections | 9/12/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 10/10/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 11/6/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 11/13/2024 | ADRIANA LOPEZ |
| Issued | 11/14/2024 | APPLICANT |
| CofO in Progress | 10/3/2025 | DAVID WILLIAMS |
| Permit Finaled | 10/4/2025 | DEROLD HAUFF |
| CofO Issued | 10/4/2025 | DEROLD HAUFF |
| Permit Finaled | 10/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/8/2024 | CELINA MORENO |
| Sewer availability | Cleared | 7/8/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2024 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 7/29/2024 | ALEXANDER HELFER |
| GPI Written Notices | Cleared | 10/10/2024 | ADRIANA LOPEZ |
Contact Information
| Contractor | United Remodeling Construction Inc; Lic. No.: 813590-B | , |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: NA93095 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/11/2024 | Approved | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 12/12/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/27/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 12/27/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 12/27/2024 | Corrections Issued | CRAIG DAVIS |
| Insulation | 12/30/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2025 | Conditional Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Partial Approval | DAVID WILLIAMS |
| HVAC-Rough | 3/6/2025 | Corrections Issued | DAVID WILLIAMS |
| PLUMBING-Rough | 3/6/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 5/21/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Rough | 5/21/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| HVAC-Rough | 5/21/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 5/21/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 5/23/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 5/23/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 5/23/2025 | Approved | DAVID WILLIAMS |
| Insulation | 6/4/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 6/4/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 6/4/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 6/9/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 6/9/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 9/22/2025 | Approved | DAVID WILLIAMS |
| Final | 9/22/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 9/22/2025 | Approved | DAVID WILLIAMS |
| HVAC-Final | 9/22/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 9/22/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 9/22/2025 | SGSOV Approved | DAVID WILLIAMS |
| Service/Power Release | 9/22/2025 | Approved | DAVID WILLIAMS |
| Smoke Detectors | 9/22/2025 | Approved | DAVID WILLIAMS |
| Final | 10/3/2025 | OK to Issue CofO | DAVID WILLIAMS |