2113 S VICTORIA AVE 90016

Certificate Information: 2113 S VICTORIA AVE 90016

Application / Permit
24014-10000-02282
Plan Check / Job No.
B24LA10110
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to and conversion of (e) detached garage to an ADU per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/24/2025
Issuing Office
Current Status
Issued on 3/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/28/2024 APPLICANT
Assigned to Plan Check Engineer 5/31/2024 REZA HAGHIGHAT
Corrections Issued 6/2/2024 REZA HAGHIGHAT
Applicant returned to address corrections 7/24/2024 REZA HAGHIGHAT
Plan Check Approved 11/7/2024 REZA HAGHIGHAT
Issued 3/24/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/12/2024 JESSICA OPINION
Roof/Waste drainage to street Cleared 7/12/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 7/16/2024 JESSICA OPINION
Sewer availability Cleared 7/16/2024 JESSICA OPINION
Construction near power lines Cleared 10/31/2024 TINA MIRANDA

Contact Information

Contractor J M E Construction; Lic. No.: 921816-B       ,
Engineer Garcia,, Lionel J; Lic. No.: NA4653       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/15/2025 Corrections Issued WILLIAM MICHALAK
Footing/Foundation/Slab 4/15/2025 Corrections Issued WILLIAM MICHALAK
Underground Mechanical 4/15/2025 Approved WILLIAM MICHALAK
Underground Mechanical 9/3/2025 Partial Approval WILLIAM MICHALAK
BUILDING-Rough-Frame 10/2/2025 Corrections Issued WILLIAM MICHALAK
ELECTRICAL-Rough 10/2/2025 Corrections Issued WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 10/2/2025 Approved WILLIAM MICHALAK
Gas Test 10/2/2025 Partial Approval WILLIAM MICHALAK
HVAC-Rough 10/2/2025 Approved WILLIAM MICHALAK
MERV13>=Rough 10/2/2025 Approved WILLIAM MICHALAK
PLUMBING-Rough 10/2/2025 Approved WILLIAM MICHALAK
Underground Mechanical 10/2/2025 Approved WILLIAM MICHALAK
Insulation 10/7/2025 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 10/7/2025 Partial Approval WILLIAM MICHALAK
Shower Pan 10/7/2025 Approved WILLIAM MICHALAK
Drywall Nailing 10/15/2025 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 10/15/2025 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 2/12/2026 Approved WILLIAM MICHALAK
Final 2/12/2026 Corrections Issued WILLIAM MICHALAK
Footing/Foundation/Slab 2/12/2026 Approved WILLIAM MICHALAK
MERV13>=Final 2/12/2026 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 2/12/2026 SGSOV Approved WILLIAM MICHALAK
Smoke Detectors 2/12/2026 Approved WILLIAM MICHALAK
Final 2/18/2026 Not Ready for Inspection WILLIAM MICHALAK
Final 2/25/2026 Conditional Approval WILLIAM MICHALAK