2701-2703 S MCCONNELL DR 90064

Certificate Information: 2701-2703 S MCCONNELL DR 90064

Application / Permit
24014-10000-02270
Plan Check / Job No.
B24LA10065
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO EXISTING 2 STORY SFD. ATTACH EXISTING GARAGE TO DWELING W/ 2ND STORY ADDITION FOR NEW ATTACHED ADU. Attached ADU per LAMC 12.22 A.33 (c) and (e).
Permit Issued
Issued on 11/20/2024
Issuing Office
Valley
Current Status
Issued on 11/20/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/28/2024 APPLICANT
Assigned to Plan Check Engineer 5/30/2024 ADRIANA LOPEZ
Corrections Issued 6/1/2024 ADRIANA LOPEZ
Quality Review Completed 6/7/2024 KEN GILL
Building Plans Picked Up 7/10/2024 APPLICANT
Applicant returned to address corrections 10/31/2024 ADRIANA LOPEZ
Plan Check Approved 11/12/2024 ADRIANA LOPEZ
Issued 11/20/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/7/2024 HISASHI KOBAYAKAWA
Permit Cleared 8/7/2024 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 8/7/2024 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 8/13/2024 HISASHI KOBAYAKAWA
Sewer availability Cleared 8/13/2024 HISASHI KOBAYAKAWA
Specific Plan Cleared 9/4/2024 FREDDY GARCIA
GPI Written Notices Cleared 11/12/2024 ADRIANA LOPEZ
Grading Pre-Inspection Cleared 11/12/2024 ADRIANA LOPEZ

Contact Information

Architect Adam, Sauer; Lic. No.: C36869       ,
Contractor D K R Construction Inc; Lic. No.: 1070450-B 7110 FOREST HILLS RD      WEST HILLS, CA 91307
Engineer Castro,, Ivan; Lic. No.: C84846 750 OTAY LAKES ROAD   #202    CHULA VISTA, CA 91910

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

ELECTRICAL-Rough 7/24/2026    Time Frame: 10-12

Inspection Request History

Footing/Foundation/Slab 2/19/2025 Corrections Issued ASHLEY THOMPSON
METHANE-Barrier 2/19/2025 Approved ASHLEY THOMPSON
METHANE-Subgrade 2/19/2025 Approved ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 2/20/2025 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Corrections Issued ASHLEY THOMPSON
Wood Frame 4/7/2025 Partial Approval EVAN COOPER
Deputy Steel/Welding 5/2/2025 Conditional Approval ASHLEY THOMPSON
Deputy Steel/Welding 5/15/2025 Conditional Approval ASHLEY THOMPSON
Deputy Steel/Welding 5/21/2025 Conditional Approval ASHLEY THOMPSON
Footing/Foundation/Slab 6/2/2025 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval ASHLEY THOMPSON
Footing/Foundation/Slab 7/2/2025 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 7/8/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Corrections Issued ASHLEY THOMPSON
Deputy Wood Construction 9/4/2025 Conditional Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Rough 11/5/2025 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 11/7/2025 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 11/19/2025 Approved ASHLEY THOMPSON
PLUMBING-Rough 11/19/2025 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 12/10/2025 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Corrections Issued ASHLEY THOMPSON
Green Building Rough 12/10/2025 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Corrections Issued ASHLEY THOMPSON
Shower Pan 1/6/2026 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 1/13/2026 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 1/15/2026 Corrections Issued ASHLEY THOMPSON
Green Building Rough 1/15/2026 Partial Approval ASHLEY THOMPSON
Interior/Exterior Lathing 1/15/2026 Partial Approval ASHLEY THOMPSON
Insulation 1/21/2026 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 1/27/2026 Partial Approval ASHLEY THOMPSON
Insulation 1/27/2026 Partial Approval ASHLEY THOMPSON
Drywall Nailing 2/2/2026 Partial Approval ASHLEY THOMPSON
Green Building Rough 2/2/2026 Not Ready for Inspection ASHLEY THOMPSON
Drywall Nailing 2/4/2026 Partial Approval RYAN SALAZAR