3015 N ACRESITE ST 90039
Certificate Information: 3015 N ACRESITE ST 90039
- Application / Permit
- 24014-10000-02255
- Plan Check / Job No.
- B24LA10001
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition and convert (E) single family dwelling (rear unit) to detached ADU per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 8/30/2024
- Issuing Office
- Current Status
- CofO Issued on 1/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2024 | SHANGQIN XIE |
| Corrections Issued | 6/4/2024 | SHANGQIN XIE |
| Applicant returned to address corrections | 7/2/2024 | SHANGQIN XIE |
| Applicant returned to address corrections | 8/19/2024 | SHANGQIN XIE |
| Applicant returned to address corrections | 8/22/2024 | SHANGQIN XIE |
| Plan Check Approved | 8/27/2024 | SHANGQIN XIE |
| Issued | 8/30/2024 | APPLICANT |
| CofO in Progress | 1/30/2026 | NICHOLAS LOPEZ |
| Permit Finaled | 1/30/2026 | DEROLD HAUFF |
| CofO Issued | 1/30/2026 | DEROLD HAUFF |
| Permit Finaled | 1/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 7/3/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 7/20/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Mejia Jose Christian; Lic. No.: 1063470-B | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/23/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 9/23/2024 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 10/8/2024 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Other (see comments) | 10/15/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/15/2024 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 10/18/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 10/28/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 10/31/2024 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/17/2025 | Partial Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 5/13/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Underground Mechanical | 5/13/2025 | Partial Approval | NICHOLAS LOPEZ |
| HVAC-Rough | 5/28/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 5/28/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 5/28/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 6/2/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 6/2/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 6/2/2025 | Approved | NICHOLAS LOPEZ |
| MERV13>=Rough | 6/2/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 6/17/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Drywall Nailing | 7/1/2025 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 7/11/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 7/21/2025 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 8/11/2025 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Final | 9/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 9/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 9/19/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 9/19/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 9/19/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| MERV13>=Final | 9/19/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 9/19/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 9/19/2025 | Approved | NICHOLAS LOPEZ |
| Final | 12/5/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 12/5/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/5/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Final | 12/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 1/30/2026 | OK to Issue CofO | NICHOLAS LOPEZ |