2137 W SANTA YNEZ ST 90026
Certificate Information: 2137 W SANTA YNEZ ST 90026
- Application / Permit
- 24014-10000-02225
- Plan Check / Job No.
- B24LA09850
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERSION OF EXISTING UNDERFLOOR AREA TO FAMILYROOM, BATHROOM AND LAUNDRYROOM (380 SF) AND ENCLOSED (54 SF) COVER PORCH FIRST FLOOR
- Permit Issued
- Issued on 10/31/2024
- Issuing Office
- Current Status
- CofO Issued on 4/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | SAM CHANG |
| Corrections Issued | 7/2/2024 | SAM CHANG |
| Quality Review Completed | 7/8/2024 | EUGENE BARBEAU |
| Applicant returned to address corrections | 8/8/2024 | SAM CHANG |
| Applicant returned to address corrections | 9/5/2024 | SAM CHANG |
| Applicant returned to address corrections | 10/8/2024 | SAM CHANG |
| Plan Check Approved | 10/29/2024 | SAM CHANG |
| Issued | 10/31/2024 | APPLICANT |
| CofO in Progress | 4/3/2026 | FREDDIE RIVERA |
| CofO Issued | 4/4/2026 | DEROLD HAUFF |
| Permit Finaled | 4/4/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/8/2024 | SAM CHANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | 1250 W GLENOAKS BLVD E355 GLENDALE, CA 91201 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 1/6/2025 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/16/2025 | Partial Inspection | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 5/16/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/20/2025 | Corrections Issued | FREDDIE RIVERA |
| Wood Frame | 5/20/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/16/2025 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 6/16/2025 | Approved | FREDDIE RIVERA |
| Final | 12/15/2025 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/15/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 12/15/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 12/15/2025 | Approved | FREDDIE RIVERA |
| Final | 2/26/2026 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/26/2026 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 3/19/2026 | OK to Issue CofO | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Approved | FREDDIE RIVERA |