101 S GREENFIELD AVE 90049

Certificate Information: 101 S GREENFIELD AVE 90049

Application / Permit
24014-10000-02223
Plan Check / Job No.
B24LA09838
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2-STORY ADDITION TO SINGLE FAMILY DWELLING WITH NEW ATTACHED GARAGE; NFPA-13D THROUGHOUT BUILDING
Permit Issued
Issued on 10/10/2024
Issuing Office
Metro
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Building Plans Picked Up 6/14/2023 APPLICANT
Submitted 5/23/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 SINA KHOSRAVI
Corrections Issued 6/7/2024 SINA KHOSRAVI
Quality Review Completed 6/7/2024 KEN GILL
Plan Check Approved 9/25/2024 SINA KHOSRAVI
Issued 10/10/2024 APPLICANT
CofO in Progress 9/17/2025 CARLOS MATAMOROS
Permit Finaled 9/18/2025 RICHARD STEINBACH
CofO Issued 9/18/2025 RICHARD STEINBACH
Permit Finaled 9/18/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/3/2024 DARIN LAM
Permit Cleared 7/3/2024 DARIN LAM
Sewer availability Cleared 7/3/2024 DARIN LAM
Grading Pre-Inspection Cleared 7/5/2024 VASIL MIHALEV
Roof/Waste drainage to street Cleared 7/23/2024 DARIN LAM
Trees in Parkway Cleared 9/11/2024 MIGUEL ORNELAS
GPI Written Notices Cleared 9/25/2024 SINA KHOSRAVI

Contact Information

Contractor Design Equity; Lic. No.: 1087681-B 20130 ROCKPORT WAY      MALIBU, CA 90265
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/1/2024 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 11/8/2024 Corrections Issued CARLOS MATAMOROS
Sewer 11/20/2024 Not Ready for Inspection CARLOS MATAMOROS
Underground Mechanical 11/20/2024 Not Ready for Inspection CARLOS MATAMOROS
Sewer 11/25/2024 Approved CARLOS MATAMOROS
Underground Mechanical 11/25/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Partial Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 2/25/2025 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 2/25/2025 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Corrections Issued STEPHANIE SWANSON
Gas Test 2/27/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 2/27/2025 Approved CARLOS MATAMOROS
HVAC-Rough 3/6/2025 Corrections Issued STEPHANIE SWANSON
Shower Pan 3/6/2025 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 3/10/2025 Corrections Issued CHRISTOPHER WILSON
Shower Pan 3/10/2025 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 3/11/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 3/11/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/11/2025 Not Ready for Inspection CARLOS MATAMOROS
Pre-Inspection 3/11/2025 Approved CARLOS MATAMOROS
Shower Pan 3/11/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 3/12/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/12/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 3/13/2025 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 3/13/2025 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/17/2025 Corrections Issued CARLOS MATAMOROS
Green Building Rough 3/17/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/24/2025 Not Ready for Inspection CHRISTOPHER WILSON
Insulation 3/26/2025 Approved CARLOS MATAMOROS
Drywall Nailing 4/4/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 4/4/2025 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 4/7/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Final 7/7/2025 Corrections Issued BOBBY KEY
ELECTRICAL-Final 7/25/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 7/25/2025 Approved TEMISTOCLES CAAL
HVAC-Final 8/21/2025 Corrections Issued CARLOS MATAMOROS
Green Building Final 9/10/2025 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 9/10/2025 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 9/12/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 9/16/2025 Approved CARLOS MATAMOROS
Final 9/16/2025 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 9/16/2025 Approved CARLOS MATAMOROS
Green Building Final 9/16/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 9/16/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 9/17/2025 Approved CARLOS MATAMOROS
Final 9/17/2025 OK to Issue CofO CARLOS MATAMOROS
Footing/Foundation/Slab 9/17/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/17/2025 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 9/17/2025 Approved CARLOS MATAMOROS