935 S DUNSMUIR AVE 90036

Certificate Information: 935 S DUNSMUIR AVE 90036

Application / Permit
24014-10000-02208
Plan Check / Job No.
B24LA09733
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(eplan) remodel (E) two-story SFD with patio addition on ground floor and 2nd floor addition for new 2 bedrooms and one bathroom.
Permit Issued
Issued on 4/4/2025
Issuing Office
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 FARSHAD ALIMOHAMADI
Corrections Issued 6/10/2024 FARSHAD ALIMOHAMADI
Quality Review Completed 7/9/2024 YOUNG KIM
Applicant returned to address corrections 10/11/2024 FARSHAD ALIMOHAMADI
Plan Check Approved 10/11/2024 FARSHAD ALIMOHAMADI
Issued 4/4/2025 APPLICANT
CofO in Progress 2/20/2026 RONNIE MINDANAO
Permit Finaled 2/23/2026 DEROLD HAUFF
CofO Issued 2/23/2026 DEROLD HAUFF
Permit Finaled 2/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/19/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/20/2024 WALLIE JONG
Sewer availability Cleared 9/20/2024 WALLIE JONG
HPOZ Cleared 9/25/2024 ERIK VAN BREENE

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Architect Rosas,, G Rafael; Lic. No.: NA32813       ,
Contractor F2c Builders Group Inc; Lic. No.: 1122970-B       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/13/2025 Approved RONNIE MINDANAO
PLUMBING-Rough 5/19/2025 Partial Approval RONNIE MINDANAO
Footing/Foundation/Slab 5/22/2025 Approved RONNIE MINDANAO
METHANE-Barrier 5/22/2025 Approved RONNIE MINDANAO
METHANE-Subgrade 5/22/2025 Approved RONNIE MINDANAO
Deputy Drilled-In Anchors 5/23/2025 Approved RONNIE MINDANAO
Deputy Drilled-In Anchors 7/1/2025 Conditional Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 7/8/2025 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Corrections Issued RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Approved RONNIE MINDANAO
HVAC-Rough 9/22/2025 Corrections Issued RONNIE MINDANAO
PLUMBING-Rough 9/22/2025 Approved RONNIE MINDANAO
ELECTRICAL-Rough 10/7/2025 Partial Approval RONNIE MINDANAO
HVAC-Rough 10/7/2025 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 10/24/2025 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Rough 10/24/2025 Not Ready for Inspection RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/24/2025 Partial Approval RONNIE MINDANAO
METHANE-Rough 10/24/2025 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 10/31/2025 Approved RONNIE MINDANAO
ELECTRICAL-Rough 10/31/2025 Approved RONNIE MINDANAO
Shower Pan 10/31/2025 Approved RONNIE MINDANAO
Insulation 11/5/2025 Partial Approval RONNIE MINDANAO
Interior/Exterior Lathing 11/5/2025 Approved RONNIE MINDANAO
Insulation 11/13/2025 Not Ready for Inspection RONNIE MINDANAO
Interior/Exterior Lathing 11/13/2025 Approved RONNIE MINDANAO
Insulation 11/17/2025 Approved RONNIE MINDANAO
Drywall Nailing 12/1/2025 Approved RONNIE MINDANAO
ELECTRICAL-Final 2/2/2026 Not Ready for Inspection RONNIE MINDANAO
Final 2/2/2026 Corrections Issued RONNIE MINDANAO
HVAC-Final 2/2/2026 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Final 2/2/2026 No Access for Inspection RONNIE MINDANAO
ELECTRICAL-Final 2/17/2026 Approved RONNIE MINDANAO
Final 2/17/2026 OK to Issue CofO RONNIE MINDANAO
HVAC-Final 2/17/2026 Approved RONNIE MINDANAO
PLUMBING-Final 2/17/2026 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Approved RONNIE MINDANAO
Smoke Detectors 2/17/2026 Approved RONNIE MINDANAO