935 S DUNSMUIR AVE 90036
Certificate Information: 935 S DUNSMUIR AVE 90036
- Application / Permit
- 24014-10000-02208
- Plan Check / Job No.
- B24LA09733
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (eplan) remodel (E) two-story SFD with patio addition on ground floor and 2nd floor addition for new 2 bedrooms and one bathroom.
- Permit Issued
- Issued on 4/4/2025
- Issuing Office
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/10/2024 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 7/9/2024 | YOUNG KIM |
| Applicant returned to address corrections | 10/11/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 10/11/2024 | FARSHAD ALIMOHAMADI |
| Issued | 4/4/2025 | APPLICANT |
| CofO in Progress | 2/20/2026 | RONNIE MINDANAO |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| CofO Issued | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/19/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2024 | WALLIE JONG |
| Sewer availability | Cleared | 9/20/2024 | WALLIE JONG |
| HPOZ | Cleared | 9/25/2024 | ERIK VAN BREENE |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Architect | Rosas,, G Rafael; Lic. No.: NA32813 | , |
| Contractor | F2c Builders Group Inc; Lic. No.: 1122970-B | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/13/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 5/19/2025 | Partial Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 5/22/2025 | Approved | RONNIE MINDANAO |
| METHANE-Barrier | 5/22/2025 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 5/22/2025 | Approved | RONNIE MINDANAO |
| Deputy Drilled-In Anchors | 5/23/2025 | Approved | RONNIE MINDANAO |
| Deputy Drilled-In Anchors | 7/1/2025 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 9/22/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 9/22/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/7/2025 | Partial Approval | RONNIE MINDANAO |
| HVAC-Rough | 10/7/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/24/2025 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/24/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Partial Approval | RONNIE MINDANAO |
| METHANE-Rough | 10/24/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/31/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/31/2025 | Approved | RONNIE MINDANAO |
| Shower Pan | 10/31/2025 | Approved | RONNIE MINDANAO |
| Insulation | 11/5/2025 | Partial Approval | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/5/2025 | Approved | RONNIE MINDANAO |
| Insulation | 11/13/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/13/2025 | Approved | RONNIE MINDANAO |
| Insulation | 11/17/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 12/1/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 2/2/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 2/2/2026 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 2/2/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Final | 2/2/2026 | No Access for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Final | 2/17/2026 | Approved | RONNIE MINDANAO |
| Final | 2/17/2026 | OK to Issue CofO | RONNIE MINDANAO |
| HVAC-Final | 2/17/2026 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 2/17/2026 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Approved | RONNIE MINDANAO |
| Smoke Detectors | 2/17/2026 | Approved | RONNIE MINDANAO |