2025-2027 S LINNINGTON AVE 90025
Certificate Information: 2025-2027 S LINNINGTON AVE 90025
- Application / Permit
- 24014-10000-02203
- Plan Check / Job No.
- B24LA09719
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED CONVERSION OF ATTACHED GARAGE/PORTION OF BREEZEWAY AND (N) ADDITION TO (N) ADU PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 10/17/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 5/25/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 6/4/2024 | APPLICANT |
| Applicant returned to address corrections | 7/1/2024 | SAMUEL GONZALEZ |
| Plan Check Approved | 7/15/2024 | FERNANDO FLORES |
| Issued | 10/17/2024 | APPLICANT |
| CofO in Progress | 3/14/2025 | DANIEL VERA |
| Permit Finaled | 3/18/2025 | RICHARD STEINBACH |
| CofO Issued | 3/18/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/18/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2024 | ANDREA SAINT-ANTONIN |
| Roof/Waste drainage to street | Cleared | 6/12/2024 | ANDREA SAINT-ANTONIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2024 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 6/17/2024 | ANDREA SAINT-ANTONIN |
| Specific Plan | Cleared | 6/20/2024 | RICHARD WOO |
| Grading Pre-Inspection | Cleared | 7/15/2024 | LAWRENCE QUIRANTE |
Contact Information
| Contractor | Radd Construction; Lic. No.: 922522-B | 26078 ADAMOR RD CALABASAS, CA 91302 |
| Engineer | Golabtounkar,, Tony Hamid; Lic. No.: C49104 | 1434 WESTWOOD BLVD ST 17 LOS ANGELES, CA 90024 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 11/13/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/13/2024 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 11/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 12/17/2024 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Subgrade | 12/17/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/17/2024 | Approved | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 12/18/2024 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 12/18/2024 | Approved | STEPHANIE SWANSON |
| METHANE-Barrier | 12/18/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2024 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 12/31/2024 | Conditional Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/31/2024 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 12/31/2024 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/31/2024 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Rough | 12/31/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/31/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 12/31/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/3/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 1/3/2025 | Approved | STEPHANIE SWANSON |
| Insulation | 1/3/2025 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 1/6/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/6/2025 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/4/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 3/4/2025 | Approved | BOBBY KEY |
| Final | 3/4/2025 | Corrections Issued | BOBBY KEY |
| Green Building Final | 3/4/2025 | Approved | BOBBY KEY |
| Green Building Rough | 3/4/2025 | Approved | BOBBY KEY |
| HVAC-Final | 3/4/2025 | Corrections Issued | BOBBY KEY |
| METHANE-Final | 3/4/2025 | Approved | BOBBY KEY |
| METHANE-Rough | 3/4/2025 | Approved | BOBBY KEY |
| PLUMBING-Final | 3/4/2025 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/4/2025 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 3/4/2025 | Approved | BOBBY KEY |
| Final | 3/13/2025 | OK to Issue CofO | DANIEL VERA |
| HVAC-Final | 3/13/2025 | Approved | DANIEL VERA |
| Service/Power Release | 3/14/2025 | Approved | DANIEL VERA |