2025-2027 S LINNINGTON AVE 90025

Certificate Information: 2025-2027 S LINNINGTON AVE 90025

Application / Permit
24014-10000-02203
Plan Check / Job No.
B24LA09719
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED CONVERSION OF ATTACHED GARAGE/PORTION OF BREEZEWAY AND (N) ADDITION TO (N) ADU PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 10/17/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2024 APPLICANT
Assigned to Plan Check Engineer 5/22/2024 LAWRENCE QUIRANTE
Corrections Issued 5/25/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 6/4/2024 APPLICANT
Applicant returned to address corrections 7/1/2024 SAMUEL GONZALEZ
Plan Check Approved 7/15/2024 FERNANDO FLORES
Issued 10/17/2024 APPLICANT
CofO in Progress 3/14/2025 DANIEL VERA
Permit Finaled 3/18/2025 RICHARD STEINBACH
CofO Issued 3/18/2025 RICHARD STEINBACH
Permit Finaled 3/18/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/11/2024 ANDREA SAINT-ANTONIN
Roof/Waste drainage to street Cleared 6/12/2024 ANDREA SAINT-ANTONIN
Eng Process Fee Ord 176,300 Cleared 6/17/2024 ANDREA SAINT-ANTONIN
Sewer availability Cleared 6/17/2024 ANDREA SAINT-ANTONIN
Specific Plan Cleared 6/20/2024 RICHARD WOO
Grading Pre-Inspection Cleared 7/15/2024 LAWRENCE QUIRANTE

Contact Information

Contractor Radd Construction; Lic. No.: 922522-B 26078 ADAMOR RD      CALABASAS, CA 91302
Engineer Golabtounkar,, Tony Hamid; Lic. No.: C49104 1434 WESTWOOD BLVD ST 17      LOS ANGELES, CA 90024

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 11/13/2024 Approved STEPHANIE SWANSON
PLUMBING-Rough 11/13/2024 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 11/14/2024 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/17/2024 Partial Approval STEPHANIE SWANSON
METHANE-Subgrade 12/17/2024 Approved STEPHANIE SWANSON
PLUMBING-Rough 12/17/2024 Approved STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/18/2024 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 12/18/2024 Approved STEPHANIE SWANSON
METHANE-Barrier 12/18/2024 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/31/2024 Conditional Approval STEPHANIE SWANSON
ELECTRICAL-Rough 12/31/2024 Corrections Issued STEPHANIE SWANSON
Gas Test 12/31/2024 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 12/31/2024 Partial Approval STEPHANIE SWANSON
METHANE-Rough 12/31/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 12/31/2024 Approved STEPHANIE SWANSON
Shower Pan 12/31/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 1/3/2025 Approved STEPHANIE SWANSON
HVAC-Rough 1/3/2025 Approved STEPHANIE SWANSON
Insulation 1/3/2025 Approved STEPHANIE SWANSON
Drywall Nailing 1/6/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 1/6/2025 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 3/4/2025 Approved BOBBY KEY
ELECTRICAL-Final 3/4/2025 Approved BOBBY KEY
Final 3/4/2025 Corrections Issued BOBBY KEY
Green Building Final 3/4/2025 Approved BOBBY KEY
Green Building Rough 3/4/2025 Approved BOBBY KEY
HVAC-Final 3/4/2025 Corrections Issued BOBBY KEY
METHANE-Final 3/4/2025 Approved BOBBY KEY
METHANE-Rough 3/4/2025 Approved BOBBY KEY
PLUMBING-Final 3/4/2025 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 3/4/2025 SGSOV Approved BOBBY KEY
Smoke Detectors 3/4/2025 Approved BOBBY KEY
Final 3/13/2025 OK to Issue CofO DANIEL VERA
HVAC-Final 3/13/2025 Approved DANIEL VERA
Service/Power Release 3/14/2025 Approved DANIEL VERA