1450 1/4-3/4 S HOLT AVE 90035

Certificate Information: 1450 1/4-3/4 S HOLT AVE 90035

Application / Permit
24014-10000-02178
Plan Check / Job No.
B24LA09630
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Converting the Detached Garage and addition into 2 ADUs PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g).
Permit Issued
Issued on 9/9/2024
Issuing Office
Current Status
CofO Issued on 8/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2024 APPLICANT
Assigned to Plan Check Engineer 5/28/2024 PINANK PATEL
Corrections Issued 5/29/2024 PINANK PATEL
Plan Check Approved 7/8/2024 PINANK PATEL
Issued 9/9/2024 APPLICANT
CofO in Progress 8/6/2025 EVAN COOPER
Permit Finaled 8/12/2025 RICHARD STEINBACH
CofO Issued 8/12/2025 RICHARD STEINBACH
Permit Finaled 8/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/4/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 6/4/2024 JEANIE LAM
Miscellaneous Cleared 6/5/2024 ALBERT TAM
Eng Process Fee Ord 176,300 Cleared 6/6/2024 JEANIE LAM
Sewer availability Cleared 6/6/2024 JEANIE LAM
"Q" conditions Cleared 7/2/2024 NOAH MCCOY

Contact Information

Contractor Matzri Bernam; Lic. No.: 995835-B       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/10/2024 Partial Inspection FARHAD DADBIN
METHANE-Rough 2/28/2025 Not Ready for Inspection AMANUEL BERHE
METHANE-Subgrade 3/4/2025 Not Ready for Inspection ARAM AVEDISIAN
Deputy Drilled-In Anchors 3/10/2025 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 3/17/2025 Conditional Approval ARAM AVEDISIAN
Special/Order Compliance 3/25/2025 Approved EVAN COOPER
Special/Order Compliance 3/26/2025 Corrections Issued MICHAEL PELHAM
Wood Frame 4/10/2025 Not Ready for Inspection MICHAEL PELHAM
Special/Order Compliance 5/23/2025 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Corrections Issued EVAN COOPER
Deputy Wood Construction 6/13/2025 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Approved EVAN COOPER
Interior/Exterior Lathing 6/18/2025 Partial Approval EVAN COOPER
Special/Order Compliance 6/18/2025 Approved EVAN COOPER
Insulation 6/24/2025 Approved EVAN COOPER
Interior/Exterior Lathing 6/24/2025 Approved EVAN COOPER
Drywall Nailing 6/30/2025 Approved ARAM AVEDISIAN
Final 7/25/2025 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 7/25/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 7/25/2025 Approved EVAN COOPER
Wood Frame 7/25/2025 Approved EVAN COOPER
Final 7/29/2025 Corrections Issued EVAN COOPER
Final 8/6/2025 OK to Issue CofO EVAN COOPER