3961 S INGLEWOOD BLVD 90066
Certificate Information: 3961 S INGLEWOOD BLVD 90066
- Application / Permit
- 24014-10000-02164
- Plan Check / Job No.
- B24LA09567
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: REMOVE ATTACHED DECK, REMODEL AND ADDITION TO (E) SINGLE FMAILY DWELLING UNIT
- Permit Issued
- Issued on 7/29/2024
- Issuing Office
- Current Status
- CofO Issued on 9/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | DANIEL YIP |
| Corrections Issued | 5/27/2024 | DANIEL YIP |
| Quality Review Completed | 5/29/2024 | GARO TELMI |
| Plan Check Approved | 7/24/2024 | DANIEL YIP |
| No Progress | 7/26/2024 | DANIEL YIP |
| Plan Check Approved | 7/26/2024 | DANIEL YIP |
| Issued | 7/29/2024 | APPLICANT |
| Permit Finaled | 9/26/2025 | RICHARD STEINBACH |
| CofO Issued | 9/26/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/26/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/4/2024 | DINAH GARIN |
| Specific Plan | Cleared | 6/24/2024 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2024 | DIANA RENTERIA |
| Roof/Waste drainage to street | Cleared | 6/26/2024 | DIANA RENTERIA |
Contact Information
| Architect | Schabel,, Craig Wesley; Lic. No.: C40563 | 2321 ZENO PLACE VENICE, CA 90291 |
| Contractor | Keefer Construction Unlimited Llc; Lic. No.: 1074095-B | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/17/2024 | Partial Inspection | JESUS PINEDA |
| Footing/Foundation/Slab | 10/1/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 10/3/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 12/3/2024 | Partial Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Conditional Approval | JESUS PINEDA |
| Special/Order Compliance | 1/6/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 2/11/2025 | Approved | EVAN COOPER |
| Shower Pan | 2/14/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 2/20/2025 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 3/11/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 3/11/2025 | Corrections Issued | MICHAEL ALLEN |
| Green Building Rough | 3/11/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 3/11/2025 | Approved | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 3/11/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 3/20/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 3/20/2025 | Partial Approval | JAYLIN GRAVITTE |
| Special/Order Compliance | 3/20/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Insulation | 3/24/2025 | Partial Approval | JESUS RODRIGUEZ |
| Special/Order Compliance | 3/24/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 3/26/2025 | Approved | JAYLIN GRAVITTE |
| Insulation | 4/2/2025 | Approved | BOBBY KEY |
| Drywall Nailing | 4/18/2025 | Corrections Issued | MICHAEL ALLEN |
| Pre-Inspection | 6/25/2025 | Approved | MICHAEL ALLEN |
| Pre-Inspection | 7/1/2025 | Approved | MICHAEL ALLEN |
| Underground Mechanical | 7/11/2025 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 9/23/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 9/23/2025 | Approved | WILBER ROSALES |
| Final | 9/23/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 9/23/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 9/23/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 9/23/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 9/23/2025 | SGSOV Approved | WILBER ROSALES |
| Service/Power Release | 9/23/2025 | Not Ready for Inspection | WILBER ROSALES |
| Smoke Detectors | 9/23/2025 | Approved | WILBER ROSALES |
| Final | 9/26/2025 | Conditional Approval | DAVID FEILER |
| Service/Power Release | 9/26/2025 | Approved | DAVID FEILER |