3542 W 59TH ST 90043
Certificate Information: 3542 W 59TH ST 90043
- Application / Permit
- 24014-10000-02149
- Plan Check / Job No.
- B24LA09524
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- E-PLAN. PROPOSED REMODEL AND ADDITION TO EXPAND (E) BEDROOM WITH NEW ATT. PATIO COVER.
- Permit Issued
- Issued on 7/15/2024
- Issuing Office
- Current Status
- CofO Issued on 7/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2024 | JOHNPAUL ISIP |
| Corrections Issued | 5/27/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 7/10/2024 | JOHNPAUL ISIP |
| Issued | 7/15/2024 | APPLICANT |
| CofO in Progress | 7/21/2025 | MICHAEL LEWIS |
| Permit Finaled | 7/21/2025 | DEROLD HAUFF |
| CofO Issued | 7/21/2025 | DEROLD HAUFF |
| Permit Finaled | 7/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/8/2024 | CELINA MORENO |
| Sewer availability | Cleared | 7/8/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2024 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 1543 HAWTHORNE, CA 90251 |
| Engineer | Hamilton,, John O; Lic. No.: NA53284 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/4/2024 | No Access for Inspection | AMIR NAZARIAN |
| Footing/Foundation/Slab | 9/17/2024 | Corrections Issued | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 9/20/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 9/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Green Building Rough | 9/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| PLUMBING-Rough | 9/27/2024 | Partial Approval | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 11/8/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 11/8/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 11/26/2024 | Partial Approval | AMIR NAZARIAN |
| ELECTRICAL-Rough | 11/26/2024 | Conditional Approval | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Approved | AMIR NAZARIAN |
| Green Building Rough | 11/26/2024 | Approved | AMIR NAZARIAN |
| HVAC-Rough | 11/26/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 11/26/2024 | Approved | AMIR NAZARIAN |
| Service/Power Release | 11/26/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 12/12/2024 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 12/12/2024 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 12/12/2024 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/12/2024 | Approved | JOHN QUINTANILLA |
| Insulation | 12/20/2024 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 12/20/2024 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 12/31/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 12/31/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 4/16/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 4/16/2025 | Approved | WAYNE REGESTER |
| Final | 4/16/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Footing/Foundation/Slab | 4/16/2025 | Approved | WAYNE REGESTER |
| Green Building Final | 4/16/2025 | Approved | WAYNE REGESTER |
| HVAC-Final | 4/16/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 4/16/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 4/16/2025 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 4/16/2025 | Approved | WAYNE REGESTER |
| Final | 7/16/2025 | Corrections Issued | SABAS ALONSO |
| Final | 7/18/2025 | OK to Issue CofO | MICHAEL LEWIS |