2225 S DUNSMUIR AVE 90016
Certificate Information: 2225 S DUNSMUIR AVE 90016
- Application / Permit
- 24014-10000-02136
- Plan Check / Job No.
- B24LA09438
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: ADDITION AND CONVERSION OF (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d).
- Permit Issued
- Issued on 4/14/2025
- Issuing Office
- Current Status
- CofO Issued on 12/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2024 | MADISON ODELL |
| Corrections Issued | 5/25/2024 | MADISON ODELL |
| Applicant returned to address corrections | 11/7/2024 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/18/2025 | GURUNATH NESARAJAH |
| Issued | 4/14/2025 | APPLICANT |
| CofO in Progress | 12/19/2025 | BRENDAN MORELLI |
| Permit Finaled | 12/19/2025 | DEROLD HAUFF |
| CofO Issued | 12/19/2025 | DEROLD HAUFF |
| Permit Finaled | 12/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/7/2024 | RIDWAN HARDY |
| Address approval | Cleared | 11/30/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2025 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 2/8/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 2/8/2025 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 6/18/2025 | Approved | ARTHUR NEGRETE |
| Sewer | 6/18/2025 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 6/18/2025 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 6/24/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 7/8/2025 | Conditional Approval | ARTHUR NEGRETE |
| Green Building Rough | 7/8/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 7/18/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 7/18/2025 | Conditional Approval | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 7/18/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 7/18/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 8/6/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 8/6/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 8/6/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 8/6/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 8/6/2025 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 8/11/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 8/11/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 8/11/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 9/16/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 9/16/2025 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 9/16/2025 | Approved | ARTHUR NEGRETE |
| Final | 10/7/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 10/7/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 10/7/2025 | Approved | ARTHUR NEGRETE |
| Final | 11/14/2025 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 11/14/2025 | SGSOV Not Ready | WILLIAM SIERRA |
| Smoke Detectors | 11/14/2025 | Approved | WILLIAM SIERRA |
| Final | 12/16/2025 | OK to Issue CofO | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Approved | BRENDAN MORELLI |