1014 W HARDING AVE 90291
Certificate Information: 1014 W HARDING AVE 90291
- Application / Permit
- 24014-10000-02115
- Plan Check / Job No.
- B24LA09377
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) DETACHED GARAGE TO ADU, WITH 2ND STORY ADDITION. DETACHED ADU PER LAMC 12.22 A.33 (c) and (d)
- Permit Issued
- Issued on 12/31/2024
- Issuing Office
- Current Status
- CofO Issued on 10/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | ADRIANA LOPEZ |
| Corrections Issued | 6/12/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 6/28/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 9/13/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 10/8/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 12/12/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 12/20/2024 | ADRIANA LOPEZ |
| Issued | 12/31/2024 | APPLICANT |
| CofO in Progress | 10/21/2025 | WILBER ROSALES |
| Permit Finaled | 10/27/2025 | RICHARD STEINBACH |
| CofO Issued | 10/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/20/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 6/20/2024 | DARIN LAM |
| Specific Plan | Cleared | 6/20/2024 | RICHARD WOO |
| Specific Plan | Cleared | 6/20/2024 | RICHARD WOO |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2024 | DARIN LAM |
| Sewer availability | Cleared | 7/1/2024 | DARIN LAM |
| ZA Case | Cleared | 8/23/2024 | ALEX VELA |
| Miscellaneous | Cleared | 8/26/2024 | ALEX VELA |
| Miscellaneous | Cleared | 8/26/2024 | ALEX VELA |
| Specific Plan | Cleared | 8/26/2024 | ALEX VELA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Jencor Construction Inc; Lic. No.: 968170-B | 19528 VENTURA BLVD 273 TARZANA, CA 91356 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/10/2025 | Approved | MICHAEL ALLEN |
| Underground Mechanical | 3/10/2025 | Approved | MICHAEL ALLEN |
| Deputy Drilled-In Anchors | 3/20/2025 | Conditional Approval | DAVID FEILER |
| ELECTRICAL-Rough | 3/26/2025 | Partial Approval | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 3/26/2025 | Corrections Issued | MICHAEL ALLEN |
| Footing/Foundation/Slab | 3/26/2025 | Conditional Approval | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 4/3/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 4/3/2025 | Approved | MICHAEL ALLEN |
| Deputy Drilled-In Anchors | 4/14/2025 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Corrections Issued | JESUS PINEDA |
| Gas Test | 5/7/2025 | Approved | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 6/9/2025 | Conditional Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 6/9/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 6/9/2025 | Conditional Approval | MICHAEL ALLEN |
| HVAC-Rough | 6/9/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 6/9/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 6/9/2025 | Corrections Issued | MICHAEL ALLEN |
| Special/Order Compliance | 6/9/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Wood Frame | 6/9/2025 | Approved | MICHAEL ALLEN |
| Insulation | 7/17/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 7/17/2025 | Partial Approval | MICHAEL ALLEN |
| Special/Order Compliance | 7/17/2025 | Corrections Issued | MICHAEL ALLEN |
| Wood Frame | 7/17/2025 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 7/23/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 7/23/2025 | Approved | WILBER ROSALES |
| Shower Pan | 7/23/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 7/29/2025 | Approved | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 10/20/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 10/20/2025 | Approved | WILBER ROSALES |
| Final | 10/20/2025 | OK to Issue CofO | WILBER ROSALES |
| Green Building Final | 10/20/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 10/20/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 10/20/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 10/20/2025 | Approved | WILBER ROSALES |