7661-7665 N PENFIELD AVE 91306
Certificate Information: 7661-7665 N PENFIELD AVE 91306
- Application / Permit
- 24014-10000-02111
- Plan Check / Job No.
- B24LA09355
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION TO (E) SFD WITH INT. AND EXT. STR. REMODEL TO HAVE PATIO COVER, ATTACHED ADU PER LAMC 12.22 A.33(c) and (e) AND CONVERT (E) ATT. GARAGE TO JADU.
- Permit Issued
- Issued on 7/11/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 5/30/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 5/31/2024 | KEN GILL |
| Building Plans Picked Up | 6/5/2024 | APPLICANT |
| Plan Check Approved | 7/11/2024 | MAHNAZ NOURHASHEMI |
| Issued | 7/11/2024 | APPLICANT |
| CofO in Progress | 4/22/2025 | ALEXANDER HANDY |
| Permit Finaled | 8/5/2025 | DANIEL ORRANTE |
| CofO Issued | 8/5/2025 | DANIEL ORRANTE |
| Permit Finaled | 8/5/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/8/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/11/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/29/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 7/29/2024 | Partial Inspection | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 8/8/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 8/9/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 8/12/2024 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 8/12/2024 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | Partial Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Gas Test | 10/7/2024 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 10/7/2024 | Approved | ARUTYUN MADATYAN |
| Sewer | 10/7/2024 | Approved | ARUTYUN MADATYAN |
| Underground Mechanical | 10/7/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 10/18/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 10/30/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 10/30/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 10/30/2024 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 11/6/2024 | Approved | ALEXANDER HANDY |
| Green Building Rough | 11/6/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 11/6/2024 | Approved | ALEXANDER HANDY |
| Shower Pan | 11/6/2024 | Approved | ALEXANDER HANDY |
| Insulation | 11/12/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 11/19/2024 | Approved | SCOTT SOBEL |
| SGSOV-Seismic Gas S/O Valve | 4/15/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| ELECTRICAL-Final | 4/18/2025 | Approved | ALEXANDER HANDY |
| Final | 4/18/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 4/18/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 4/18/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 4/18/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/18/2025 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 4/18/2025 | Approved | ALEXANDER HANDY |
| Smoke Detectors | 4/18/2025 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 4/28/2025 | Corrections Issued | ALEXANDER HANDY |