1495 N DOHENY DR 90069

Certificate Information: 1495 N DOHENY DR 90069

Application / Permit
24014-10000-02084
Plan Check / Job No.
B24LA09241
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING WITH ATTACHED 2- CAR GARAGE .
Permit Issued
Issued on 2/17/2025
Issuing Office
Current Status
Issued on 2/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/16/2024 APPLICANT
Assigned to Plan Check Engineer 5/30/2024 JAD BASMA
Corrections Issued 6/5/2024 JAD BASMA
Quality Review Completed 6/21/2024 GARO TELMI
Applicant returned to address corrections 7/24/2024 JAD BASMA
Applicant returned to address corrections 8/27/2024 JAD BASMA
Plan Check Approved 1/2/2025 JAD BASMA
Issued 2/17/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/26/2024 MICHAEL TEMPLE
Eng Process Fee Ord 176,300 Cleared 8/27/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 8/27/2024 JEANIE LAM
Sewer availability Cleared 8/27/2024 JEANIE LAM
Hydrant and Access approval Cleared 11/7/2024 KURT CORRAL
ZA Case Cleared 12/24/2024 RUBEN VASQUEZ
GPI Written Notices Cleared 1/2/2025 JAD BASMA

Contact Information

Contractor Hm Dg Inc; Lic. No.: 962205-B       ,

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

HVAC-Rough 6/8/2026   
ELECTRICAL-Rough 6/8/2026   

Inspection Request History

Pre-Inspection 3/26/2025 Partial Inspection BRENDAN MORELLI
Deputy Drilled-In Anchors 5/9/2025 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 5/15/2025 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 5/20/2025 Approved BRIAN SULLIVAN
Wood Frame 6/3/2025 Corrections Issued RAUL BARAJAS
Wood Frame 6/6/2025 Partial Approval ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Partial Approval CRAIG VAUGHAN
Underground Mechanical 9/18/2025 Partial Approval CRAIG VAUGHAN
Underground Mechanical 11/3/2025 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 2/27/2026 Approved DAVID WILLIAMS
ELECTRICAL-Rough 3/17/2026 Not Ready for Inspection DAVID WILLIAMS
PLUMBING-Rough 3/17/2026 Partial Approval DAVID WILLIAMS
Underground Mechanical 3/17/2026 Partial Approval DAVID WILLIAMS
Underground Mechanical 4/6/2026 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 5/26/2026 Approved BRENDAN MORELLI