5420 N TROOST AVE 91601
Certificate Information: 5420 N TROOST AVE 91601
- Application / Permit
- 24014-10000-02076
- Plan Check / Job No.
- B24LA09218
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED REC ROOM WITH ADDITION TO BECOME DETACHED 1 STORY ADU PER ENGINEER DESIGN (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | AUNG SOE |
| Corrections Issued | 5/21/2024 | AUNG SOE |
| Building Plans Picked Up | 5/24/2024 | APPLICANT |
| Plan Check Approved | 11/18/2024 | ALEXANDER JOO |
| Issued | 11/21/2024 | APPLICANT |
| CofO in Progress | 12/4/2025 | JAVIER RAMOS JR |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
| CofO Issued | 12/26/2025 | RUBEN SALAS |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 10/25/2024 | ALEX VELA |
| Address approval | Cleared | 10/28/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 10/28/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 10/29/2024 | CARLOS RAMIREZ |
| Specific Plan | Cleared | 10/29/2024 | JOANNA MARROQUIN |
| Construction near power lines | Cleared | 11/15/2024 | EDGAR PASCUA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 12/16/2024 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/3/2025 | Conditional Approval | JOSE AVILA |
| Sewer | 1/3/2025 | Approved | JOSE AVILA |
| Underground Mechanical | 1/3/2025 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 1/10/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 1/10/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 2/28/2025 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 5/6/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/6/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/6/2025 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/6/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/6/2025 | Corrections Issued | JAVIER RAMOS JR |
| MERV13>=Rough | 5/6/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/6/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/2/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/2/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 6/2/2025 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/2/2025 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 6/2/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/9/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 6/9/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/9/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/26/2025 | Corrections Issued | JAVIER RAMOS JR |
| Final | 11/26/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 11/26/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 11/26/2025 | Corrections Issued | JAVIER RAMOS JR |
| MERV13>=Final | 11/26/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 11/26/2025 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 11/26/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 12/2/2025 | Approved | JAVIER RAMOS JR |
| Final | 12/2/2025 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Final | 12/2/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 12/2/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Final | 12/4/2025 | OK to Issue CofO | JAVIER RAMOS JR |