5420 N TROOST AVE 91601

Certificate Information: 5420 N TROOST AVE 91601

Application / Permit
24014-10000-02076
Plan Check / Job No.
B24LA09218
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED REC ROOM WITH ADDITION TO BECOME DETACHED 1 STORY ADU PER ENGINEER DESIGN (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 11/21/2024
Issuing Office
Metro
Current Status
CofO Issued on 12/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2024 APPLICANT
Assigned to Plan Check Engineer 5/16/2024 AUNG SOE
Corrections Issued 5/21/2024 AUNG SOE
Building Plans Picked Up 5/24/2024 APPLICANT
Plan Check Approved 11/18/2024 ALEXANDER JOO
Issued 11/21/2024 APPLICANT
CofO in Progress 12/4/2025 JAVIER RAMOS JR
Permit Finaled 12/26/2025 RUBEN SALAS
CofO Issued 12/26/2025 RUBEN SALAS
Permit Finaled 12/26/2025 RUBEN SALAS

Permit Application Clearance Information

Miscellaneous Cleared 10/25/2024 ALEX VELA
Address approval Cleared 10/28/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 10/28/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 10/29/2024 CARLOS RAMIREZ
Sewer availability Cleared 10/29/2024 CARLOS RAMIREZ
Specific Plan Cleared 10/29/2024 JOANNA MARROQUIN
Construction near power lines Cleared 11/15/2024 EDGAR PASCUA

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/16/2024 Partial Inspection CHRISTOPHER ROJAS
Pre-Inspection 12/16/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 1/3/2025 Conditional Approval JOSE AVILA
Sewer 1/3/2025 Approved JOSE AVILA
Underground Mechanical 1/3/2025 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 1/10/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/10/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 2/28/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 5/6/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 5/6/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 5/6/2025 Approved JAVIER RAMOS JR
Green Building Rough 5/6/2025 Approved JAVIER RAMOS JR
HVAC-Rough 5/6/2025 Corrections Issued JAVIER RAMOS JR
MERV13>=Rough 5/6/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 5/6/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/2/2025 Approved JAVIER RAMOS JR
HVAC-Rough 6/2/2025 Approved JAVIER RAMOS JR
Insulation 6/2/2025 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 6/2/2025 Partial Approval JAVIER RAMOS JR
Shower Pan 6/2/2025 Approved JAVIER RAMOS JR
Drywall Nailing 6/9/2025 Approved JAVIER RAMOS JR
Insulation 6/9/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/9/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 11/26/2025 Corrections Issued JAVIER RAMOS JR
Final 11/26/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 11/26/2025 Approved JAVIER RAMOS JR
HVAC-Final 11/26/2025 Corrections Issued JAVIER RAMOS JR
MERV13>=Final 11/26/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 11/26/2025 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 11/26/2025 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 11/26/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/2/2025 Approved JAVIER RAMOS JR
Final 12/2/2025 Partial Approval JAVIER RAMOS JR
HVAC-Final 12/2/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 12/2/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV Approved JAVIER RAMOS JR
Final 12/4/2025 OK to Issue CofO JAVIER RAMOS JR