7426 N DENNY AVE 91352
Certificate Information: 7426 N DENNY AVE 91352
- Application / Permit
- 24014-10000-02071
- Plan Check / Job No.
- B24VN04792
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN NEW ADDITION TO EXISTING SFD + NEW PORCH +LAUNDRY+NEW CARPORT
- Permit Issued
- Issued on 11/6/2024
- Issuing Office
- Current Status
- CofO Issued on 6/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | SUNMIN LEE |
| Corrections Issued | 5/16/2024 | SUNMIN LEE |
| Quality Review Completed | 5/23/2024 | GARO TELMI |
| Applicant returned to address corrections | 6/10/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 9/27/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 10/29/2024 | SUNMIN LEE |
| Plan Check Approved | 11/1/2024 | SUNMIN LEE |
| Issued | 11/6/2024 | APPLICANT |
| CofO in Progress | 5/6/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 6/12/2025 | RUBEN SALAS |
| CofO Issued | 6/12/2025 | RUBEN SALAS |
| Permit Finaled | 6/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 6/14/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 9/23/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/23/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/23/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
| Engineer | Sanchez,, Carlos Gabriel; Lic. No.: L9120 | 228 E LIME AVE MONROVIA, CA 91016 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/8/2024 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 11/8/2024 | Partial Approval | JOSE AVILA |
| Deputy Drilled-In Anchors | 11/25/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/27/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 12/3/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/31/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 1/31/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 1/31/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 1/31/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/31/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/4/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 2/4/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 2/4/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 2/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 2/4/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 2/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 2/7/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 2/7/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 2/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 2/13/2025 | Approved | JOSE AVILA |
| Final | 4/22/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 4/22/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 4/22/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 4/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 4/24/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 4/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 4/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 4/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/6/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |