7426 N DENNY AVE 91352

Certificate Information: 7426 N DENNY AVE 91352

Application / Permit
24014-10000-02071
Plan Check / Job No.
B24VN04792
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN NEW ADDITION TO EXISTING SFD + NEW PORCH +LAUNDRY+NEW CARPORT
Permit Issued
Issued on 11/6/2024
Issuing Office
Current Status
CofO Issued on 6/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 SUNMIN LEE
Corrections Issued 5/16/2024 SUNMIN LEE
Quality Review Completed 5/23/2024 GARO TELMI
Applicant returned to address corrections 6/10/2024 SUNMIN LEE
Applicant returned to address corrections 9/27/2024 SUNMIN LEE
Applicant returned to address corrections 10/29/2024 SUNMIN LEE
Plan Check Approved 11/1/2024 SUNMIN LEE
Issued 11/6/2024 APPLICANT
CofO in Progress 5/6/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 6/12/2025 RUBEN SALAS
CofO Issued 6/12/2025 RUBEN SALAS
Permit Finaled 6/12/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/13/2024 EDGAR ALCARAZ
Sewer availability Cleared 6/14/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 9/23/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 9/23/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/23/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606
Engineer Sanchez,, Carlos Gabriel; Lic. No.: L9120 228 E LIME AVE      MONROVIA, CA 91016

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/8/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 11/8/2024 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 11/25/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 11/27/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 12/3/2024 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/31/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/31/2025 Partial Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 1/31/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 1/31/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 1/31/2025 Partial Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/4/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/4/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/4/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 2/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/4/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 2/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 2/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 2/13/2025 Approved JOSE AVILA
Final 4/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/22/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/22/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/22/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/24/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 4/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/24/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 4/24/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/24/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 5/6/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ