12430 1/2 W MITCHELL AVE 90066
Certificate Information: 12430 1/2 W MITCHELL AVE 90066
- Application / Permit
- 24014-10000-02053
- Plan Check / Job No.
- B24LA09096
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ACCESSORY DWELLING UNIT WITH ATTACHED 1-CAR GARAGE PER LAMC 12.22A.33(c)-(d). SOLAR INSTALLATION TO MEET 1.95KW AS REQUIRED BY TITLE 24 PRIOR TO COFO
- Permit Issued
- Issued on 6/5/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 6/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | VIVIAN LAO |
| Corrections Issued | 6/6/2024 | VIVIAN LAO |
| Quality Review Completed | 6/7/2024 | KEN GILL |
| Building Plans Picked Up | 6/11/2024 | APPLICANT |
| Applicant returned to address corrections | 9/10/2024 | VIVIAN LAO |
| Plan Check Approved | 10/30/2024 | VIVIAN LAO |
| Issued | 6/5/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/30/2024 | RIDWAN HARDY |
| Address approval | Cleared | 10/16/2024 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2024 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 10/16/2024 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 10/16/2024 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 10/17/2024 | JOSHUA JONES |
Contact Information
| Contractor | True North Designs; Lic. No.: 541817-B | 12430 MITCHELL AVENUE LOS ANGELES, CA 90066 |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/26/2025 | Approved | MICHAEL ALLEN |
| Underground Mechanical | 6/26/2025 | Approved | MICHAEL ALLEN |
| Deputy Wood Construction | 8/8/2025 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Partial Approval | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 10/1/2025 | Partial Approval | WILBER ROSALES |
| BUILDING-Rough-Frame | 10/30/2025 | Partial Approval | WILBER ROSALES |
| ELECTRICAL-Rough | 10/30/2025 | Partial Approval | WILBER ROSALES |
| Green Building Rough | 10/30/2025 | Approved | WILBER ROSALES |
| HVAC-Rough | 10/30/2025 | Partial Approval | WILBER ROSALES |
| PLUMBING-Rough | 10/30/2025 | Approved | WILBER ROSALES |
| Verify Sprinkler Sign Off | 10/30/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 11/19/2025 | Partial Approval | WILBER ROSALES |
| ELECTRICAL-Rough | 11/19/2025 | Partial Approval | WILBER ROSALES |
| HVAC-Rough | 11/19/2025 | Approved | WILBER ROSALES |
| Insulation | 12/3/2025 | Partial Approval | WILBER ROSALES |
| Shower Pan | 12/3/2025 | Approved | WILBER ROSALES |
| Drywall Nailing | 12/22/2025 | Partial Approval | WILBER ROSALES |
| Interior/Exterior Lathing | 12/22/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 2/26/2026 | Not Ready for Inspection | DAKOTA LOW |
| ELECTRICAL-Rough | 2/26/2026 | Not Ready for Inspection | DAKOTA LOW |
| Underground Mechanical | 2/26/2026 | Not Ready for Inspection | DAKOTA LOW |
| Underground Mechanical | 3/4/2026 | Partial Approval | DAKOTA LOW |
| BUILDING-Rough-Frame | 4/8/2026 | Approved | DAKOTA LOW |
| Drywall Nailing | 4/8/2026 | Approved | DAKOTA LOW |
| ELECTRICAL-Rough | 4/8/2026 | Approved | DAKOTA LOW |
| Insulation | 4/8/2026 | Approved | DAKOTA LOW |
| Sewer | 4/8/2026 | Approved | DAKOTA LOW |