2819 S PALM GROVE AVE 90016

Certificate Information: 2819 S PALM GROVE AVE 90016

Application / Permit
24014-10000-02044
Plan Check / Job No.
B24LA09056
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 14' X 19'10" DETACHED GARAGE AND (N) 22'9" X 23'8" IRREG SHAPED ADDITION (471 SF) TO (N) ACCESSORY DWELLING UNIT (723 SF) PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 9/3/2024
Issuing Office
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2024 APPLICANT
Assigned to Plan Check Engineer 5/20/2024 MADISON ODELL
Corrections Issued 5/20/2024 MADISON ODELL
Applicant returned to address corrections 8/16/2024 MADISON ODELL
Plan Check Approved 8/30/2024 PINANK PATEL
Issued 9/3/2024 APPLICANT
CofO in Progress 4/30/2025 ENRIQUE MIRELES
Permit Finaled 5/15/2025 DEROLD HAUFF
CofO Issued 5/15/2025 DEROLD HAUFF
Permit Finaled 5/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 8/9/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 8/13/2024 ERIK BEASLEY
Sewer availability Cleared 8/13/2024 ERIK BEASLEY
Address approval Cleared 8/16/2024 KHAING AYE
Roof/Waste drainage to street Cleared 8/16/2024 KHAING AYE
Hold Cleared 9/20/2024 SANDRA SOH

Contact Information

Contractor Domus Design Build Llc; Lic. No.: 1107347-B       ,
Engineer Kim,, Taewon; Lic. No.: C80632 28531 PALOS VERDES DR EAST      RANCHO PALOS VERDES, CA 90275

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/17/2024 Approved JUSTIN HAWLEY
Underground Mechanical 10/17/2024 Partial Approval JUSTIN HAWLEY
Deputy Drilled-In Anchors 10/24/2024 Conditional Approval JUSTIN HAWLEY
Footing/Foundation/Slab 10/29/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 12/2/2024 Not Ready for Inspection JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 12/2/2024 Partial Approval JUSTIN HAWLEY
Wood Frame 12/2/2024 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Rough 12/18/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 12/18/2024 Corrections Issued JUSTIN HAWLEY
Green Building Rough 12/18/2024 Not Ready for Inspection JUSTIN HAWLEY
HVAC-Rough 12/18/2024 Approved JUSTIN HAWLEY
PLUMBING-Rough 12/18/2024 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 12/27/2024 Corrections Issued JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Approved JUSTIN HAWLEY
Insulation 12/27/2024 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 1/13/2025 Partial Approval ANTHONY RAMOS
BUILDING-Rough-Frame 1/24/2025 Approved JUSTIN HAWLEY
Drywall Nailing 1/24/2025 Approved JUSTIN HAWLEY
Green Building Rough 1/24/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 2/3/2025 Approved JUSTIN HAWLEY
Sewer 4/1/2025 Approved JOSH MEISTER
PLUMBING-Rough 4/4/2025 Approved LUIS CASTRO
Underground Mechanical 4/4/2025 Approved LUIS CASTRO
Final 4/22/2025 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/22/2025 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/22/2025 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 4/22/2025 Approved ENRIQUE MIRELES
Green Building Final 4/25/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 4/29/2025 Approved ENRIQUE MIRELES
Final 4/29/2025 OK to Issue CofO ENRIQUE MIRELES
HVAC-Final 4/29/2025 Approved ENRIQUE MIRELES
PLUMBING-Final 4/29/2025 Approved ENRIQUE MIRELES