14738 W OTSEGO ST 91403

Certificate Information: 14738 W OTSEGO ST 91403

Application / Permit
24014-10000-02021
Plan Check / Job No.
B24LA08966
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
***ePlan** Addition and Major Alteration remodel to (E) Single Family Dwelling, to create new 2-story S.F.D. w/ attached Garage and Fron Trellis. --1 of 3---
Permit Issued
Issued on 8/15/2024
Issuing Office
Current Status
CofO Issued on 10/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2024 APPLICANT
Assigned to Plan Check Engineer 5/16/2024 EDWIN ESPIN
Corrections Issued 5/20/2024 EDWIN ESPIN
Quality Review Completed 5/30/2024 CHIHARU SUZUKI
Applicant returned to address corrections 8/6/2024 EDWIN ESPIN
Plan Check Approved 8/15/2024 EDWIN ESPIN
Issued 8/15/2024 APPLICANT
CofO in Progress 9/29/2025 JACK KARGODORIAN
CofO Issued 10/28/2025 RUBEN SALAS
Permit Finaled 10/28/2025 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 6/10/2024 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 6/10/2024 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 6/11/2024 MARKOS PEREZ-BRAN
Sewer availability Cleared 6/11/2024 MARKOS PEREZ-BRAN
ZI Cleared 7/3/2024 DANIEL CORONADO
Trees in Parkway Cleared 7/26/2024 DYNL MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/12/2024 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 11/22/2024 Approved JACK KARGODORIAN
Deputy Reinf. Concrete 11/25/2024 Conditional Approval JUAN VALENZUELA
Wood Frame 12/10/2024 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 1/13/2025 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Approved JACK KARGODORIAN
Green Building Rough 1/13/2025 Approved JACK KARGODORIAN
HVAC-Rough 1/13/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 1/13/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 2/4/2025 Partial Approval KEVIN BERBERYAN
Insulation 2/11/2025 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 2/11/2025 Not Ready for Inspection JACK KARGODORIAN
Shower Pan 2/11/2025 Approved JACK KARGODORIAN
Insulation 2/12/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 2/12/2025 Partial Approval JACK KARGODORIAN
Drywall Nailing 2/14/2025 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 2/14/2025 Approved JACK KARGODORIAN
Drywall Nailing 2/19/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 6/16/2025 Approved JACK KARGODORIAN
Green Building Final 6/16/2025 Approved JACK KARGODORIAN
HVAC-Final 6/16/2025 Approved JACK KARGODORIAN
PLUMBING-Final 6/16/2025 Approved JACK KARGODORIAN
Service/Power Release 6/16/2025 Corrections Issued JACK KARGODORIAN
Service/Power Release 6/20/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 9/29/2025 Approved JACK KARGODORIAN
Final 9/29/2025 OK to Issue CofO JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/29/2025 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 9/29/2025 Approved JACK KARGODORIAN