3923 W REVERE AVE 90039

Certificate Information: 3923 W REVERE AVE 90039

Application / Permit
24014-10000-02011
Plan Check / Job No.
B24LA08937
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1-STORY ADDITIONS AND MAJOR REMODEL OF (E) SFD. INCLUDES REFRAMED ROOF OF ENTIRE BLDG. (NFPA 13D THRU OUT)
Permit Issued
Issued on 11/12/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2024 APPLICANT
Assigned to Plan Check Engineer 5/16/2024 LAWRENCE QUIRANTE
Corrections Issued 5/18/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 5/20/2024 APPLICANT
Applicant returned to address corrections 6/12/2024 MINA HABILI
Applicant returned to address corrections 7/18/2024 AUNG SOE
Plan Check Approved 8/20/2024 SHANGQIN XIE
No Progress 10/23/2024 EDWIN MARTINEZ
Plan Check Approved 11/8/2024 JOHN MESIAS
Issued 11/12/2024 APPLICANT
CofO in Progress 5/7/2025 NICHOLAS LOPEZ
Permit Finaled 5/10/2025 DEROLD HAUFF
CofO Issued 5/10/2025 DEROLD HAUFF
Permit Finaled 5/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 7/27/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 7/30/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 8/6/2024 WALLIE JONG
Specific Plan Cleared 8/16/2024 JACQUELINE TORRES
Roof/Waste drainage to street Cleared 10/29/2024 DAVID LOPEZ
Sewer availability Cleared 10/29/2024 DAVID LOPEZ
Specific Plan Cleared 10/29/2024 ROSALINDA MEZA

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/14/2024 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 11/21/2024 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 11/22/2024 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 12/13/2024 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 12/24/2024 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/17/2025 Partial Approval THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 1/17/2025 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 1/21/2025 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 1/21/2025 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 1/23/2025 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 1/28/2025 Corrections Issued THOMAS LOGRASSO
Insulation 1/28/2025 Conditional Approval THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 1/28/2025 Approved THOMAS LOGRASSO
Drywall Nailing 2/3/2025 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 2/7/2025 Partial Approval ALIZAH MAYAGOITIA
Shower Pan 2/7/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/21/2025 Approved THOMAS LOGRASSO
Drywall Nailing 2/21/2025 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 2/21/2025 Approved THOMAS LOGRASSO
Green Building Rough 2/21/2025 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 2/21/2025 Approved THOMAS LOGRASSO
Green Building Final 4/28/2025 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 4/28/2025 Not Ready for Inspection NICHOLAS LOPEZ
Final 4/30/2025 Corrections Issued NICHOLAS LOPEZ
Smoke Detectors 4/30/2025 Approved NICHOLAS LOPEZ
Final 5/7/2025 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 5/7/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Approved NICHOLAS LOPEZ